November 6, 2017

For the week of November 6, 2017
Crews are removing bridge rail on
the Siuslaw Bridge Monday night through Thursday morning this week on the
northeast side of the bridge. Work will begin at 8 p.m. each night going on
into the next morning. This is a noisy process that has to be done at night
because a lane closure is needed to do the work. Daytime lanes closures are not
allowed past 11 a.m.
There will be single lane closures for bridge rail saw cutting
and bridge rail removal work. Delays may be up to 20 minutes, but will normally
be five minutes or less.
 Background
The Siuslaw River Bridge Cathodic Protection Project
is repairing damaged concrete, replacing bridge railings, and constructing
sidewalk features at the bridge ends. A major portion of the project is to
install cathodic protection that includes a zinc surface coating to protect the
structure from corrosion. Sandblasting the bridge and spraying the zinc coating
are noisy operations that must be done separately, in containment structures.
The project is scheduled to be completed in March 2019. More information
on the project is available at http://www.Siuslawbridge.com.
|
|