U.S. 20 west end curve 2-hour closures scheduled overnight

U.S. 20 Corvallis-Newport

Highway construction Update - Summer 2017

West End Curve Construction and Paving Projects

 

June 13, 2017   

west end curve blast results

West End Curve 2-hour closures

West End Curve

As you may have heard, Friday afternoon’s blast on the site did not go as planned. More materials was moved than expected and part of the highway was buried with car-sized rocks. One lane of the road reopened two hours later. As one lane of the road was to remain closed for another week, this was not a problem, other than the additional need to remove the rest of the material.

What is an issue is the size and amount of the remaining material on the hillside, and the proximity to the highway. Removing it all as it sits in close proximity to the roadway is a public safety concern.

To keep travelers and our crews safe, remove the remaining materials, and move forward with construction, we need to change the construction schedule this week. The plan is to have up to three nights of multiple two hour closures. The multiple closures will allow crews to safely move the pile of material and establish a safe slope before traffic is released. By holding traffic for two hour segments, rather than for longer times, we hope that the impact on travelers will be manageable. 

U.S. 20 full closure times at the west end curve the nights of Wednesday, June 14 and Thursday, June 15 will be:

  • 7:30 p.m. – 9:30 p.m. (open 9:30 p.m. - 10 p.m.)
  • 10 p.m. – 12 a.m. (midnight) (open midnight - 12:30 a.m.)
  • 12:30 a.m. – 2:30 a.m. (open 2:30 a.m. - 3 a.m.)
  • 3 a.m. – 5 a.m. (one lane open from 5 a.m. on through the day)

If additional cleanup time is needed, we will use Monday night, June 19 on the same schedule. The road will be open between full closure times to clear traffic. 

Message boards are placed at:

  • in Philomath at U.S. 20/OR 34
  • in Newport on U.S. 20
  • and on boards located near each end of the project (one east, one west)

Additional blasting will be needed to complete construction, but a schedule has not yet been finalized.

Background: The west end curve is the last half mile of roadway to be built for the U.S. 20 Pioneer Mountain – Eddyville Project and is scheduled to be completed in September. The curve in the existing roadway is being straightened by moving the roadway away from the river.

The main portion of the project, a 5.5 mile new alignment, opened on October 11, 2016. This new roadway replaces a ten mile segment of the original 1917-built U.S. 20 that has narrow lanes and sharp curves. The original roadway is now called Crystal Creek Loop and can be accessed at Eddyville and near the west end curve.

Travelers should expect occasional delays of 20 minutes or less in the construction area. Most work will be occurring off of the existing roadway. There will be some blasting on site, so travelers should be aware that longer closures could occur.

Paving projects on U.S. 20 continue as previously scheduled.

 

 

      odot logo

      For updates

      Construction information and related travel impacts will be available on TripCheck.com, Twitter, and the project webpages. The Oregon Department of Transportation will have a new website in late June, and so links to project pages will be changing at that time.