ODOT Region 4 Weekly Construction Report

Having trouble viewing this email? View it as a Web page.

Central Oregon Road Construction UPDATE: Week of July 18, 2016

 For further information contact:

Peter Murphy

541-388-6224

 

The Oregon Department of Transportation (ODOT) is continuing to invest in Oregon’s future with roadway improvement projects throughout Oregon’s central region (ODOT Region 4). ODOT is committed to providing a safe, efficient transportation system. The following projects reflect ODOT’s commitment to make improvements as traffic numbers rise and to make the roadways safer and more efficient for drivers. All work is dependent on weather conditions. Red denotes new or updated information.

 

DESCHUTES COUNTY

 

US 97: Romaine Village Way to Lava Butte

 

Construct widening of west side shoulder, slopes, install median barrier, and paving.

 

For the week of July 18th, 2016. The Contractor will be performing excavation and embankment operations for the southbound shoulder on the west side of the highway. Base rock will also be placed and compacted on the west side of the highway as well. South bound right lane closure will remain in place into August.

 

US97 @ Wickiup Jct. (La Pine)

Project Consists of Bridge, Earthwork, and Drainage along US97.

 

For the week of July 18th, 2016. The Contractor will continue to place embankment on the East and West side of the BNSF tracks on the new mainline alignment to its designed grades. Electrical work for illumination and fiber optic cable is set to begin. Bridge work will continue with concrete being poured on Friday for the fascia wall at Bent 2.

 

http://www.oregon.gov/ODOT/HWY/REGION4/pages/us97_wickiup_jct/us97_wickiup_jct.aspx

 

Region 4 HSIP Transition Urban The Dalles, Bend & Klamath Falls

Signal work.

 

For the week of July 18th, 2016. Contractor installing new vehicle and pedestrian signal heads and backboards in The Dalles. Work will occur at the intersection of W 6th and Cherry Hts, 2nd & Webber, and 6th and Webber with flaggers controlling the traffic at the intersections.

 

US97 J Street Intersection (Madras South Y) Sec.

 

For the week of July 11th, 2016. Contractor to perform plant establishment work.

 

http://www.oregon.gov/ODOT/HWY/REGION4/Pages/US97-RomaineVW-LavaButte.aspx

 

KLAMATH COUNTY

OR 140: Ritter Rd. – Deer Run Rd. (Bly Mtn.)

This project will reconstruct 9.2 miles of OR 140 in the Bly Mountain area (from Ritter Road to Deer Run Road). The intersection of OR 140 and the Bly Mountain Cutoff Road will be realigned.

 

Excavation, Embankment, Aggregate Base placement, sign installation and shoulder work. One lane traffic controlled by flaggers and pilot cars 24 hours / 7 days a week. Expect delays up to 20 minutes.

 

http://www.blymtn.com

 

LAKE COUNTY

US395: Alkali Lake – Lake Abert

 

Signs and delineator installation. Expect minor delays.

 

http://www.oregon.gov/ODOT/HWY/REGION4/Pages/US395-AlkaliLake-LakeAbert.aspx

 

WASCO COUNTY

I-84: The Dalles – Fifteenmile Creek

Project consists of concrete paving and bridge construction on I84 within the city limits of The Dalles.

 

For the week of July 11th, 2016. The Contractor will not be working on site.

 

I-84 is reduced to a single lane in both the east and westbound direction. Speeds have been reduced to 50mph through the construction zone.

 

http://www.oregon.gov/ODOT/HWY/REGION4/Pages/I84-TheDalles-FifteenmileCr.aspx

 

I-84: Mosier to The Dalles

Project consists of paving, and the installation of new median barrier.

 

For the week of July 18th, 2016. The Contractor will be cleaning and painting barrier..

 

I-84 will be reduced to a single lane in both the east and westbound direction. Speeds have been reduced to 50mph through the construction zone. Work hours: Sunday 7pm to Friday 11am.

 

http://www.oregon.gov/ODOT/HWY/REGION4/Pages/I84-Mosier-TheDalles.aspx

 

US 97: Moro to Madras

KERR Contractors will be replacing 29 miles of pavement on U.S. 97 between Grass Valley (MP 27.1) and Shaniko (MP 56.7). The project also includes the construction of passing lanes between MP 43.8 and MP 45.4, installation of new highway signs between Moro and Madras, and adding ADA compliant sidewalk ramps in Grass Valley.

 

For the week of July 11th, 2016. The Contractor will not be working onsite.

 

Both NB and SB lanes will be controlled by flagger and pilot cars through the work zone. Expect delays under 20 minutes.

 

http://www.oregon.gov/ODOT/HWY/REGION4/Pages/US97-Moro-Madras.aspx

####