Phase: Asphalt pavement work
Traffic Control: The right lane of eastbound NW Expressway will be closed between Villa Ave. and Pennsylvania Ave. There will be two thru lanes open, as well as the right-turn and left-turn lanes during this time. The right lane of southbound Pennsylvania Ave. will also be closed between NW Expressway and NW 50th St.
Estimated Construction Timeline: 1/16/23 - 1/18/23
back to top
Phase: Platform and sidewalk construction
Traffic Control: The right lane of southbound Classen Blvd. will be closed between NW 43rd St. and NW 41st St. There will be two southbound lanes open during this time.
Estimated Construction Timeline: 1/16/23 – 1/24/23
back to top
Phase: Wrap-up waterline work
Traffic Control: The right lane of southbound Classen Blvd. will be closed between NW 14th St. and NW 13th St. There will be two southbound lanes open during this time.
Estimated Construction Timeline: 1/16/23 – 1/20/23
back to top
Phase: Platform and sidewalk construction
Traffic Control: Eastbound NW 10th St. will be narrowed and traffic will be shifted between Lee Ave. and Dewey Ave. There will be one eastbound and one westbound lane open during this time.
Estimated Construction Timeline: 1/16/23 – 1/18/23
back to top
Phase: Traffic signal improvements
Traffic Control: Southbound Broadway Ave. will be closed between Main St. and Park Ave. There will be two northbound lanes open during this time.
Estimated Construction Timeline: 1/16/23 – 1/27/23
back to top
|
|
Hi there!
I am EMBARK's project manager for the RAPID's first bus rapid transit (BRT) Northwest line. If you have any questions about the project or anything referenced in this update, please do not hesitate to contact me.
Public transit is always a work in progress, but we know that where public transit goes, community grows. Thank you for your patience throughout the construction process.
Kristen Torkelson, Sr. Project Manager
Email Kristen |
|
|