Here's the latest on the ramp that's currently closed at Greenlawn Ave.
and some upcoming changes to I-71 NB near Stringtown Rd. to help alleviate congestion.

I-71 NB at Greenlawn Avenue

  • The ramp from Greenlawn Ave. to I-71 NB will reopen by 5 AM Monday, Sept. 24.
  • By Monday morning, all NB lanes of I-71 between Greenlawn Ave. and I-70 will be shifted to the right. This will allow crews to work on the median lanes.

I-71 NB at Stringtown Road and I-270

  • Starting Saturday morning, weather permitting, the left lane of I-71 NB will NO LONGER end at Stringtown Road.
  • The TWO left lanes will be for I-71 NB thru traffic and the right lane will be exit only to I-270.
  • Morning commuters that normally use the Stringtown Road entrance ramp to I-71 NB should consider using SR 665 to I-71 NB as an alternate route.
  • Taking SR 665 to I-71 NB will put drivers in the two thru lanes to the left of the barrier wall instead of the single lane to the right of the wall.
  • Crews will also extend the merge length on the ramp from I-270 WB to I-71 NB. This work will be complete by Saturday, weather permitting.

For more information contact: Breanna Badanes at 740-833-8222


OHGO.com logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.


The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.