 Please note that construction schedules are subject to change due to weather, site issues, etc.
Reference this MAP to view the impacted construction areas and expected lane/road changes next week for the areas referenced below.
NORTH LINDEN 1 - Construction Update Week of August 25, 2025
Notice: Sidewalk Closures and No Parking along E Weber (between Bremen / Greenwich) at various times through the week.
HUDSON-MCGUFFEY
Area 1: 1497–1517 E. Weber Rd. – Sanitary lateral lining
Area 2: E. Weber Rd. (Greenwich St. / Cleveland Ave.) – Green infrastructure installation
Area 3: Manchester Ave. (Ontario St. / Cleveland Ave.) – Water line service connections, permanent pavement replacement, & green infrastructure installation
Area 4: 1490–1520 Manchester Ave. – Sanitary lateral lining
Area 5: Aberdeen Ave. (Bremen St. / Greenwich St.) – Green infrastructure installation
Area 6: 1505–1531 Minnesota Ave. – Sanitary lateral lining
Area 7: Genessee Ave. (Hamilton Ave. / Ontario St.) – Green infrastructure installation
Area 8: 1498–1524 Genessee Ave. – Sanitary lateral lining
Area 9: Arlington Ave. (Bremen St. / Cleveland Ave.) – Green infrastructure installation
Area 10: Medina Ave. (Linden Park Dr. / E. Weber Rd.) – Green infrastructure installation
AGLER-BERRELL
No Scheduled Work
ARTANE-PARKWOOD
No Scheduled Work
OAKLAND PARK-MEDINA
No Scheduled Work
Unsure about which is your area? Visit the Blueprint map and enter your address to find out!
Sump pump installations are offered for a limited time only! Contact us and we’ll get you on the waitlist for your no-obligation assessment!
Reminder: If you have a basement backup (sewer water coming up from your floor drain), please report this to the City by calling 614-645-7102. Please note that crews are working diligently to investigate issues throughout the city, so response will not be immediate. We appreciate your patience and understanding.
|