Reminder: If you have a basement backup (sewer water coming up from your floor drain), please report this to the City by calling 614-645-7102. Please note that crews are working diligently to investigate issues throughout the city, so response will not be immediate. We appreciate your patience and understanding.
Hilltop 1 Construction Update - Week of of May 19, 2025
Eureka/Fremont
Construction Activities
- Storm sewer installation on S Richardson Ave between Wicklow Rd and Palmetto St
- Storm sewer installation on Fremont St between S Burgess Ave and S Terrace Ave
- Waterline installation on S Wayne Ave between Fremont St and Palmetto St
- Work at land bank basins 1 & 6, respectively, at 506 S Ogden Avenue and 29 S Wayne Avenue
Traffic Impacts
- Temporary closures will be utilized with signed detours
Have a question or concern about construction? Give us a call at 614-645-1253 or email blueprint@columbus.gov.
|
|
|
|