 Please note that construction schedules are subject to change due to weather, site issues, etc.
Reference this MAP to view the impacted construction areas and expected lane/road changes for next week.
North Linden - 1 Construction Update Week of October 21, 2024
Important Notice: Temporary lane/road shifts or closures are noted on the map.
OAKLAND PARK-MEDINA
Area 1: 2848-2864 Norwood St. -- Sanitary Lateral Lining
Area 2: 2773-2859 Dresden St. -- Sanitary Lateral Lining
Area 3: 1451-1471 Melrose Ave. -- Sanitary Lateral Lining
Area 4: 1446-1486 E. Weber Rd. -- Sanitary Lateral Lining
HUDSON-MCGUFFEY
Area 5: 1265-1330 E. Weber Rd. -- Permeable Pavers Installation
Area 6: 2742-2790 Ontario St. -- Green Infrastructure Installation
Area 7: 2600-2645 Ontario St. -- Green Infrastructure Installation
Area 8: 1229-1285 Genessee Ave. -- Sanitary Lateral Lining
Area 9: 2325-2762 Dresden St. -- Green Infrastructure Installation (Road Traffic Impact - see map)
Area 10: 1492-1570 E. Weber Rd. -- Permeable Pavers Installation
Area 11: 1453-1457 Arlington Ave. -- Sanitary Lateral Lining
Area 12: 1444-1585 Myrtle Ave. -- Sanitary Lateral Lining
Area 13: 1570 Briarwood Ave. -- Sanitary Lateral Lining
AGLER-BERRELL
Area 14: Aberdeen Ave. -- Downspout Installations
ARTANE-PARKWOOD
No Scheduled Work
Reminder -- View the map for details about road/lane changes for next week.
Unsure about which is your area? Visit the Blueprint map and enter your address to find out!
Sump pump installations are offered for a limited time only! Contact us and we’ll get you on the waitlist for your no-obligation assessment!
Reminder: If you have a basement backup (sewer water coming up from your floor drain), please report this to the City by calling 614-645-7102. Please note that crews are working diligently to investigate issues throughout the city, so response will not be immediate. We appreciate your patience and understanding.
|