MEDIA CONTACT: Jace Radke | 702.229.2205 | 702.249.3514 | jradke@lasvegasnevada.gov
POSTPONED - POSTPONED - POSTPONED
Sheep Mountain Parkway North To Kyle Canyon Road Opening Postponed
Project Includes Repaving And Extension Of Existing Trail
A ribbon-cutting event that was scheduled to take place on Thursday, Dec. 11, has been postponed. Final project checklist work is being completed for a new two-lane roadway extension of Sheep Mountain Parkway north from Iron Mountain Road to Kyle Canyon Road in northwest Las Vegas.The city will be providing information on when this project will open to traffic in the near future.
The project will result in 1,800-linear-feet of new two-lane roadway and includes repaving of Kyle Canyon Road from Rufus Road to Alpine Ridge Way. Intersections at Kyle Canyon and Iron Mountain roads with Sheep Mountain Parkway will be improved, and the existing trail along Sheep Mountain Parkway will be extended to Kyle Canyon Road.
The project was budgeted at $7.7 million, with funds provided by the city of Las Vegas. The contractor is Las Vegas Paving Corporation, and the design consultant is Westwood Professional Services Inc.
###
|