Durango Drive Pavement Improvements Begin April 18

CLV News Release

David Riggleman | Director of Communications | 702.229.2207


April 18, 2018 | FOR IMMEDIATE RELEASE

MEDIA CONTACT: MARGARET KURTZ | 702.229.6993 | 702.249.1828


Durango Drive Pavement Improvements Begin April 18

Work Will Continue Next Eight Weeks Between Farm Road And Brent Lane

 

Starting Wednesday, April 18, and continuing through the next eight weeks, utility adjustments, milling and paving operations will occur on Durango Drive between Farm Road and Brent Lane. Work hours will be 7 a.m. to 5 p.m., Monday through Friday. Traffic generally will be restricted to one lane in each direction north- and southbound from 7 a.m. to 5 p.m. each work day. Primary work activities of milling and overlay repaving will take approximately one week within the eight-week schedule, subject to equipment availability. Following the overlay, there will be small work zones while utilities/manholes are raised to be flush with the new pavement.

 

Buffalo Drive and Skye Canyon Park Drive are recommended as alternate routes for north- and southbound traffic.

 

Preliminary work was completed last spring and earlier this year, and consisted of improvements to sidewalk areas to meet federal Americans with Disabilities Act requirements, milling and overlay of dense-grade pavement, and removal and reconstruction of deteriorated areas of pavement. The current work consists of pavement milling, a thin lift overlay, concrete median islands, a pedestrian flasher at the intersection with Brent Lane, and new striping. Upon completion of the project, the roadway will have the appearance and ride quality of a new roadway.

 

Las Vegas Paving Corporation is the contractor. City of Las Vegas staff are managing the project. The estimated cost of the project is $1 million, with funding provided by the Southern Nevada Regional Transportation Commission’s Fuel Revenue Indexing tax.

###