The City of Minneapolis is rehabilitating the historic Nicollet Ave Bridge over Minnehaha Creek. The bridge was built in 1923 and repaired in 1973. Currently, the bridge is 63 feet wide and 816 feet long. The bridge is eligible for listing on the National Register of Historic Places. Rehabilitating it will allow use for many years to come. The bridge currently has:
- Bike lanes on both sides; Sidewalks; Two lanes for vehicles
We'll replace and fix all structural elements of the bridge and roadway. The repaired bridge will be 60’-4” wide. The bridge will have:
- 6-ft. wide protected bike lanes; 8-ft. wide pedestrian sidewalks; Two 11-ft. traffic lanes
Minnehaha Creek protections
Progress on Nicollet Ave Bridge reconstruction
- Bridge deck removal – Arch span 3 over creek
- Arch rib & pier concrete surface repairs – Span 8, piers 7 & 8
- Floor beam & column removals – Spans 5 & 6
- Bike and pedestrian trail closure beneath the bridge – details in ‘Traffic impacts’ below
- Large construction equipment
- Construction activities from 7 a.m. to 6 p.m. M-F, and some Saturdays
- Disruption, noise & dust
- Neighborhood traffic impacts
- Business access – Nicollet Ave. south of bridge open to all businesses at all times
Minnehaha Parkway is closed effective February 23, 2026. Minnehaha parkway bike and pedestrian trails will close for four weeks beginning on April 24, 2026.
The Nicollet Ave bridge closed to all traffic on March 2, 2026 and will remain closed through late 2027.
Traffic calming measures may be implemented in the project work area. When they are installed, we will share this specific information
Nicollet Ave Bridge, vehicle detours map
Nicollet Ave Pedestrian & bicycle detour map - Begins April 24, 2026
Minnehaha Pkwy Trail Pedestrian & bicycle detour map - Begins April 24, 2026
Join us at the Nicollet Ave Bridge over Minnehaha Creek bi-weekly stakeholder meeting. The meetings will provide an overview of the project, construction details, and upcoming project work information. The next bi-weekly stakeholder meeting be on Thursday, May 21, 2026.
- Every other Thursday
- 2 – 3 p.m
This is a virtual meeting using Microsoft Teams. To participate in the meeting, please click on the link provided below.
Join the Nicollet Ave Bridge over Minnehaha Creek bi-weekly stakeholder meeting
Please note: Accessing a Teams meeting via your mobile device may require downloading the Microsoft Teams app to your mobile device.
- Call in, audio only participation: 612-276-6670
- Phone Conference ID: 607 364 505#
Visit the project website and sign-up for updates: Nicollet Ave. Bridge Over Minnehaha Creek - City of Minneapolis (minneapolismn.gov)
Email Meseret Wolana, Project Engineer : Meseret.Wolana@minneapolismn.gov
Email Ahmed Omar, Construction Engineer : Ahmed.Omar@minneapolismn.gov
Contact the Project Team with project questions or comments: NicolletBridgeOverMinnehaha@minneapolismn.gov
|