Nicollet Ave. Bridge over Minnehaha Creek - Project update

PW project updates

Nicollet Ave. Bridge over Minnehaha Creek

February 9, 2026

Nicollet Ave. Bridge over Minnehaha Creek: Project overview

The City of Minneapolis will rehabilitate the historic Nicollet Ave Bridge over Minnehaha Creek. The Nicollet Ave. bridge over Minnehaha Creek is also known as Bridge No. 90591. The bridge was built in 1923 and repaired in 1973. Currently, the bridge is 63 feet wide and 816 feet long. The bridge is eligible for listing on the National Register of Historic Places. Repairing it will allow use for many years to come.

The bridge currently has:

  • Bike lanes on both sides
  • Sidewalks
  • Two lanes for vehicles

We'll replace and fix all structural elements of the bridge and roadway. The repaired bridge will be 60’-4” wide.

The bridge will have:

  • 6-foot wide protected bike lanes
  • 8-foot wide pedestrian sidewalks
  • Two 11-foot traffic lanes

Open house

NIcollet Ave. Bridge over Minnehaha Creek - Pre-Construction Virtual Open House

Please join us virtually to learn more about the project and ask a question of the project staff. Construction on the Nicollet Avenue bridge over Minnehaha Creek is anticipated to begin February 23, 2026. For those unable to attend, we will be sharing a video recording of the open house on the project web page.

  • Thursday, February 19, 2026
  • 4 – 5 p.m.

This is a virtual meeting using Microsoft Teams. To participate in the meeting, please click on the link provided below.

Join the Nicollet Ave Bridge over Minnehaha Creek Pre-Construction Open House

Please note: Accessing this Pre-Construction Open House via your mobile device may require downloading the Microsoft Teams app to your mobile device.


Construction update

Construction activity on the Nicollet Avenue bridge over Minnehaha Creek is anticipated to begin February 23, 2026. In coordination with the construction start, it is anticipated the Nicollet Ave bridge will be closed to all traffic week of March 2, 2026. More construction details and schedule to follow.


Traffic impacts

It is anticipated the Nicollet Ave bridge will be closed to all traffic week of March 2, 2026.


Stay connected

Visit the project website and sign-up for updates: Nicollet Ave. Bridge Over Minnehaha Creek - City of Minneapolis (minneapolismn.gov)

Email Petru Vizoli, Project Engineer : Petru.Vizoli@minneapolismn.gov

Email Ahmed Omar, Construction Engineer : Ahmed.Omar@minneapolismn.gov

Contact the Project Team with project questions or comments: NicolletBridgeOverMinnehaha@minneapolismn.gov


Nicollet bridge

View of Nicollet Ave. bridge looking north


For reasonable accommodations or alternative formats please contact 311.

People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000. TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia, llame al 311. Rau kev pab 311. Hadii aad Caawimaad u baahantahay 311