The City will reconstruct Hennepin Ave. between W. Lake St. and Douglas Ave. Construction will be phased over 2-years. Phase 1 will be from Lake St W to 26th St occurring in 2024. Phase 2 will be from 26th St to Douglas Ave occurring in 2025.
The project is an opportunity to update Hennepin Avenue to meet the public’s current and future needs. The new, multimodal design improves space for people walking, riding transit, biking and driving. The layout also provides space for enhanced stations being built for the future METRO E Line.
- Phase 1 Hennepin Ave from Lake to 26th St. is open to traffic. There will be short term lane and intersection closures scheduled for Saturday Oct. 4th to perform some asphalt mill and overlay repairs
- Phase 2 work from 26th to Douglas is nearing completion with misc concrete work, landscaping, sod installation, signal wiring, and final asphalt paving activities taking place.
- Hennepin is closed from Douglas to 24th. Hennepin will open to 2-way traffic next week from 24th to 26th for business access.
View Latest Construction & Traffic Impact Update PDF
- Roadwork and utility work involves use of heavy equipment that will increase noise, vibration, and dust in work areas.
- Traffic delays and detours
- Traffic lanes will be closed or restricted. These restrictions will vary by block depending on construction activity.
- Cross street lane restrictions will reduce travel lanes to 1-lane at times.
- Parking lanes will be closed during construction.
- Business access will remain open during the construction activities.
- Pedestrian detours around work areas will be set up as needed to enable construction. Greater impacts can be expected at intersections where work is occurring.
- The weekly stakeholder meetings are held virtually every Friday morning at 10 a.m.
- The meeting will help us provide you with more detailed information about the work progress update and discuss any concerns or questions you have about the project.
- This is a virtual meeting using Microsoft Teams. To participate in the meeting, please click on the link provided below
Join the weekly stakeholder meeting
Please note: Accessing the weekly stakeholder meeting via your mobile device may require downloading the Microsoft Teams app to your mobile device.
Visit the project page: www.minneapolismn.gov/government/projects/hennepin-ave-s/
Contact the construction engineer: Justin Gese, jgese@sehinc.com, or 612-209-0731
Contact the project engineer: Adam Hayow, adam.hayow@minneapolismn.gov or 612-673-2172
|