1st Ave S Reconstruction: Project update

PW project updates

1st Ave S Reconstruction 

July 12, 2024

Project overview

The Minneapolis Public Works Department plans to reconstruct 1st Ave. S from Lake St. to Franklin Ave., including replacing the Midtown Greenway Bridge. In addition to new pavement, the project will include new sidewalks, an off-street bicycle facility, updated safety features, sanitary and storm main replacement, and green stormwater infrastructure.


Construction updates

Upcoming 28th St. and 1st Ave. S intersection closure

As crews continue to work on sewer and roadway construction, a month-long closure of the 1st Ave. S and 28th St. intersection will be needed beginning Thursday, July 18. Drivers will need to follow the posted detour and use Blaisdell Ave., Lake St. and Park Ave. The intersection is expected to reopen August 16.

intersection 28th St and 1st Ave s

1st Ave. S closure

First Ave. S will continue to be closed through the fall and drivers will need to follow the posted detour route.

  • First Ave. S is closed between 27th St. and Lake St. through the fall
  • Vehicle detour route: Lake St., Lyndale Ave. and Franklin Ave.
  • Bicycle detour route: Lake St., Blaisdell Ave. and Nicollet Ave., and Franklin Ave.
first avenue south project area, bike detour

What went on this past week

  • Crews continued to excavate the ground and installed erosion control in preparation for the bridge foundation work.
  • Pile driving for the new bridge foundations began on Thursday, July 11.
  • Sanitary sewer work continues from between 27th St. and 28th St. The intersection of 27th St. remains closed.
  • Storm sewer work continues from between Lake St. and up to the bridge over the Midtown Greenway. This work does not affect the greenway.

What to expect next week

  • Expect additional noise, dust, and vibration as crews continue to work on the 1st Ave. bridge.
  • Pile driving for the new bridge foundations will continue through Friday, July 19.
  • 28th St. and 1st Ave. S intersection closure begins on Thursday, July 18.

greenway bridge

Crews working on the storm sewer near the Midtown Greenway bridge.


Upcoming events

First Ave. S Reconstruction field hours

The project team is available to answer questions every week. Come visit us to learn more:

  • Thursdays
  • 1:00 - 2:00p.m.
  • Wesley Andrews Coffee & Tea, 111 E 26th St., Minneapolis, MN 55404

Stay connected

Visit the project website; Sign up for project updates: 

minneapolismn.gov/government/projects/1st-ave-lake-st/

Contact the Project Engineer: Tracy Lindgren,

tracy.lindgren@minneapolismn.gov or 612-290-5898

Contact the transportation engineer: Abdullahi Abukar,

abdullahi.abukar@minneapolismn.gov or 612-673-2463

Email info@firstavesouth.com

Contact the project hotline with questions, comments or concerns: 612-451-0300

For an overall picture of construction activity throughout Downtown Minneapolis:

https://www.minneapolismn.gov/getting-around/parking-driving/road-closures-map/


Visit the project website; Sign up for project updates:  minneapolismn.gov/government/projects/1st-ave-lake-st/

Contact the project engineer: Tracy Lindgren,

tracy.lindgren@minneapolismn.gov or 612-290-5898

Contact the transportation engineer: Abdullahi Abukar, abdullahi.abukar@minneapolismn.gov or 612-673-2463

Email info@firstavesouth.com

Contact the project hotline with questions, comments or concerns: 612-451-0300

For an overall picture of construction activity throughout Downtown Minneapolis:

https://www.minneapolismn.gov/getting-around/parking-driving/road-closures-map/

 

For reasonable accommodations or alternative formats please contact 311.

People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000. TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia, llame al 311. Rau kev pab 311. Hadii aad Caawimaad u baahantahay 311