City of Minneapolis: 1st Ave S Reconstruction

PW project updates

1st Ave S Reconstruction 

June 21, 2024

Project overview

The Minneapolis Public Works Department plans to reconstruct 1st Ave. S. from Lake St. to Franklin Ave. including replacing the Midtown Greenway Bridge. In addition to new pavement, the project will include new sidewalks, an off street bicycle facility, updated safety features, sanitary and storm main replacement, and green stormwater infrastructure


Construction update

Lake Street Closure

Beginning Friday evening, June 21, Lake St. will be closed while crews work on sewer and roadway construction. The closure will extend from Nicollet Ave. to Stevens Ave. and is anticipated to last through Thursday, June 27.

Upcoming  Lake Street Closure

Midtown Greenway closure

The Midtown Greenway closed Monday, June 3 for crews to demolish the 1st Ave. S bridge. The detour goes from Nicollet Ave. to 5th Ave. S using 28th St. Due to unmarked material discovered during demolition, the greenway is anticipated to open Monday, June 24.

Midtown Greenway Closure

1st Ave S Closure

1st Ave S Closure

First Ave. S will continue to be closed through the fall and drivers will need to follow the posted detour route.

  • First Ave. S is closed between 27th St. and Lake St. through the fall
  • Vehicle detour route: Lake St., Lyndale Ave. and Franklin Ave.
  • Bicycle detour route: Lake St., Blaisdell Ave. and Nicollet Ave., and Franklin Ave.

What went on this past week?

  • The Midtown Greenway remained closed (see above for details).
  • Crews continued to remove a sanitary main buried under the greenway and place a concrete-encased water main under the greenway.
  • Crews removed the top layer of road along 1st Ave. S from 27th St. to the greenway.

What to expect next week?

  • Expect additional noise, dust, and vibration as crews continue to work on the 1st Ave. bridge.
  • No parking on 1st Ave. S from 27th St. to the greenway while crews work on raising sanitary sewer access covers.

Upcoming events

First Ave. S Reconstruction Field Hours

The project team is available to answer questions every week. Come visit us to learn more:

  • Thursdays
  • 1:00- 2:00p.m.
  • Wesley Andrews Coffee & Tea

111 E 26th St., Minneapolis, MN 55404


Stay connected

Visit the project website; Sign up for project updates: minneapolismn.gov/government/projects/1st-ave-lake-st/

Contact the project engineer: Tracy Lindgren,
tracy.lindgren@minneapolismn.gov or 612-290-5898

Contact the transportation engineer: Abdullahi Abukar,
abdullahi.abukar@minneapolismn.gov or 612-673-2463

Email info@firstavesouth.com

Contact the project hotline with questions, comments or concerns: 612-451-0300

For an overall picture of construction activity throughout Downtown Minneapolis:

https://www.minneapolismn.gov/getting-around/parking-driving/road-closures-map/


For reasonable accommodations or alternative formats please contact 311.

People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000. TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia, llame al 311. Rau kev pab 311. Hadii aad Caawimaad u baahantahay 311