The Cities of Minneapolis and Columbia Heights are in the process of reconstructing 37th Ave NE between Central Ave and Stinson Blvd, and 37th Pl NE between 37th Ave NE and Stinson Blvd.
The project includes complete replacement of the street infrastructure including curb and gutter, roadway pavement, driveway aprons and sidewalk. New medians will be installed at key intersections to provide better access to a new shared-use trail on the north side of 37th Ave NE. This project also features wide boulevards on both the north and south side of the street. Boulevards will feature green storm water infrastructure to help capture and treat surface water runoff before it is collected in the storm sewer system.
ACTIVITES IN THIS WEEK
- Sidewalk installation between Johnson St and Polk St on the south side of 37th.
- Boulevard topsoil - Project wide.
- Miscellaneous concrete work - Project wide.
ACTIVITIES FOR THE UPCOMING WEEK:
- Installing of sidewalk, driveways and alleys will continue on the remaining portions up to Central intersection on the south side of 37th.
- Miscellaneous work (grading, correction, tree trench energy dissipaters...) - Project wide.
TRAFFIC IMPACT
It will stay the same as it was last week.
-
Central intersection -
- The northbound traffic has no right turn access at 37th intersection
- The south bound traffic has no left tern at the intersection.
- Eastbound closed for through traffic. Due to the construction work, the lane restriction will continue.
- The eastbound general traffic detour: Central ↔ 40th Ave NE ↔Stinson Blvd.
-
Between Central Ave and Johnson St
- The westbound lane is open to traffic
- The eastbound of 37th closed and will remain closed due to activities in the stretch. However, It's accessible for local traffic.
- All side streets are open to traffic.
- Alleys on the south side of 37th temporary will be closed for the removal process.
-
Between Johnson St and Stinson Blvd.
-
Stinson intersection
WEEKLY STAKEHOLDER MEETING
- The project holds a weekly stakeholder meeting every Thursdays between 10:30 a.m. and 11:00 a.m. using Microsoft Team Meeting Virtually. Please use the link below or the link in the project web page.to join the meeting.
Join the 37th Ave NE Project Weekly Stakeholder Meeting
- The meeting will helps us to give you more detail information about the work progress update weekly bases and to have discussion on any concerns or question you have about the project. Please send me an email or give me a call if you have difficulty using the link above.
For more information, please visit the project website link below.
https://www.minneapolismn.gov/government/projects/37th-ave-ne-reconstruction/
Thank you !
Visit the project website and sign-up for updates:
https://www.minneapolismn.gov/government/projects/37th-ave-ne-reconstruction
www.37thavene.com/
Contact the project team:
Ayalew Getaneh, Project Manager, 612-499-7557, Ayalew.Getaneh@minneapolismn.gov
Charles Oliver C. Field Inspector, 612-247-0977, Charles.Oliverjr@minneapolismn.gov
|