The Cities of Minneapolis and Columbia Heights are in the process of reconstructing 37th Ave NE between Central Ave and Stinson Blvd, and 37th Pl NE between 37th Ave NE and Stinson Blvd.
The project includes complete replacement of the street infrastructure including curb and gutter, roadway pavement, driveway aprons and sidewalk. New medians will be installed at key intersections to provide better access to a new shared-use trail on the north side of 37th Ave NE. This project also features wide boulevards on both the north and south side of the street. Boulevards will feature green storm water infrastructure to help capture and treat surface water runoff before it is collected in the storm sewer system.
CONSTRUCTION STAGES
The reconstruction has two stages and two phases in each stage. However, with different conditions and unknown circumstances the stages orders might change.
Stage 1: Phase 1 (Johnson to Stinson Blvd - The north side of 37th Ave NE/ westbound)
(37th Place - 37th Ave NE to Stinson Blvd)
Phase 2 (Johnson St to Stinson Blvd. - The south side of 37th/ eastbound)
Stage 2: Phase 1 (Johnson St to Central Ave - The north side of 37th Ave NE/ westbound)
Phase 2 (Johnson St to Central Ave - The south side of 37th Ave NE/eastbound)
MAJOR ACTIVITES DONE IN THIS WEEK
- The required Traffic control and detours signs installed
- Pavement removal has been completed at Stage 1 - Phase 1
Traffic control at the Stinson Blvd intersection
Pavmement removal at stage 1 pahse 1
pavmement removal
pavement removal at 37th Pl
There will be no activities this weekend and on Monday (Memorial Day).
Next week: Stage 1 Phase 1
- The construction of the storm sewer system will begin .
TRAFFIC IMPACT
- The 37th Ave westbound road segment between Jonson St and Stinson Blvd will remain closed for through traffic. However, local access for residents and businesses will be maintained.
- The eastbound of 37th Ave NE is open for local traffic.
- 40th Ave NE is the general traffic detour route, which connect Stinson Blvd and 37th Ave NE through Central Ave NE or vice versa.
WEEKLY STAKEHOLDER MEETING
- The project holds a weekly stakeholder meeting every Thursdays between 10:30 a.m. and 11:00 a.m. using Microsoft Team Meeting Virtually. Please use the link below to join the meeting.
Join the weekly Stakeholder meeting
- The meeting will helps us to give you more detail information about the work progress update weekly bases and to have discussion on any concerns or question you have about the project. Please send me an email or give me a call if you have difficulty using the link above. If no one joins the meeting within 15 minutes, the meeting will end, but you can still contact us via phone or email.
For more information about the project and on how to attend the virtual meeting, please visit the project website link below.
https://www.minneapolismn.gov/government/projects/37th-ave-ne-reconstruction/
If you have any questions, feel free to contact us.
Thank you!
Visit the project website and sign-up for updates:
https://www.minneapolismn.gov/government/projects/37th-ave-ne-reconstruction
www.37thavene.com/
Contact the project team:
Ayalew Getaneh, Project Manager, 612-499-7557, Ayalew.Getaneh@minneapolismn.gov
Abel Yemer C. Field Inspector, 612-599-0351, Abel.Yemer@minneapolismn.gov
|