 We have updated our construction map for the METRO E Line. You can find it at the top of our project web page.
Dates are approximate and subject to change. There will be no work on May 26 in observance of Memorial Day. As the construction season continues, crews may begin Saturday work at specific locations to maintain the overall project schedule. Future newsletter updates will include details where known.
Week of June 23:
- Crews will construct sidewalks and roadway surfaces.
Week of June 30:
- Crews stripe the roadway and erect signage.
Week of June 23:
- Crews will switch traffic control to the northeast corner of the intersection.
- Crews will work on underground utilities.
- Crews will begin sawcutting and removal of concrete.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Week of June 30:
- Crews will work on underground utilities.

Week of June 23:
- Crews will work on underground utilities.
- Crews will grade surfaces in preparation for concrete work.
Week of June 30:
- Crews will construct curb, sidewalk, and roadway surfaces.
 *Please note that the above detour will not go into effect until the week of June 16
Week of June 23:
- Crews will continue sawcutting, removal of concrete, and grading on the north side of the intersection.
- Crews will construct sidewalks.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Week of June 30:
- Crews will construct curb, gutter, and roadway surfaces.
Week of June 23:
- Crews will continue to grade surfaces and construct sidewalks.
Week of June 30:
- Crews will strip the roadway and erect signage.
Week of June 23:
- Crews will continue to grade surfaces and construct sidewalks and bike lanes.
Week of June 30:
- Crews will continue to grade surfaces and construct sidewalks and bike lanes.
- Crews will stripe the intersection and erect signage.
*Please note: The image above is a bicycle detour.
Week of June 23:
- Crews will shift traffic control to the roadway.
- Crews will work on underground utilities.
- Crews will work on sawcutting and removal of concrete.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Week of June 30:
- Crews will continue sawcutting and removal of concrete.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Week of June 23:
- Crews will construct curb, gutter, sidewalk, and roadway surfaces.
- Crews will work on underground utilities.
Week of June 30:
- Crews will construct sidewalks.
Week of June 23:
- Crews will work on underground utilities.
- Crews will grade and construct sidewalks.
Week of June 30:
- Crews will work on underground utilities.
- Crews will grade and construct sidewalks.
Week of June 23:
- Crews will construct roadway surfaces and sidewalks.
- Crews will stripe the roadway and finish site cleanup.
- Crews will remove traffic control.
- Following the completion of civil construction, work is focused on installation of lighting and E Line platform amenities. We will update this section when we have timelines for this work.
Week of June 23:
- Crews will construct new roadway surfaces and sidewalks.
- Crews will shift work to the north side of the intersection.
- Crews will begin sawcutting and removal of concrete on the north side of the intersection.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Week of June 30:
- Crews will work on underground utilities.
- Crews will continue sawcutting and removal of concrete on the north side of the intersection.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Following the completion of civil construction, work is focused on installation of lighting and E Line platform amenities. We will update this section when we have timelines for this work.
Note: The City of Edina is currently constructing sidewalks along the east side of France Avenue between 60th and 62nd streets. This is not METRO E Line work. To learn more about this project or if you have a concern, please reach out to Chad Millner at the City of Edina.
Following the completion of civil construction, work will be focused on installation of E Line platform amenities. We will update this section when we have timelines for this work.
Note: The City of Edina is currently reconstructing 65th Street east of Drew Avenue. This is not METRO E Line work. To learn more about this project or if you have a concern, please see the City’s project website.
- Access to Southdale Hospital and Southdale Medical Center parking lots and garages will be maintained during construction.
- France Avenue can be accessed from the Hospital and Medical Center by taking Drew Avenue to 66th Street.
Week of June 23:
- Crews will stripe the roadway and finish site cleanup.
- Following the completion of civil construction, work is focused on installation of lighting and E Line platform amenities. We will update this section when we have timelines for this work.
|