 We have updated our construction map for the METRO E Line. You can find it at the top of our project web page.
Dates are approximate and subject to change. There will be no work on May 26 in observance of Memorial Day. As the construction season continues, crews may begin Saturday work at specific locations to maintain the overall project schedule. Future newsletter updates will include details where known.
Week of June 9:
- Crews will construct sidewalk and roadway surfaces.
Week of June 16:
- Crews will construct sidewalks.
- Crews will work on underground utilities.
Week of June 9:
- Crews will continue sawcutting and removal of concrete on the north side of the intersection.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
- Crews will continue work on underground utilities.
- Crews will grade surfaces in preparation for concrete work.
Week of June 16:
- Crews will grade surfaces and construct curb, gutter, sidewalk, and roadway surfaces.

Week of June 9:
- Crews will work on site restorations.
Week of June 16:
- Crews will shift work to the north side of the intersection.
- The below detour will go into effect.
- Crews will begin sawcutting and removal of concrete on the north side of the intersection.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
- Crews will work on underground utilities.
 *Please note that the above detour will not go into effect until the week of June 16
Week of June 9:
- Crews will grade surfaces before constructing sidewalks.
Week of June 16:
- Crews will continue constructing sidewalks.
- Crews will stripe the area and shift traffic control to the north side of the intersection.
- Crews will begin sawcutting, removal of concrete, and grading on the north side of the intersection.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Week of June 9:
- Crews will continue to construct new roadway surfaces.
- Crews will adjust pedestrian traffic control before they begin sawcutting and removal of remaining concrete on sidewalks.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Week of June 16:
- Crews will work on underground utilities.
- Crews will continue grading surfaces and constructing sidewalks.
Week of June 9:
- Crews will continue to construct new roadway surfaces.
- Crews will work on underground utilities.
Week of June 16:
- Crews will continue to work on underground utilities.
- Crews will grade surfaces and construct sidewalks.
*Please note: The image above is a bicycle detour.
Week of June 9:
- Crews will continue sawcutting, removal of concrete, and grading in preparation for concrete work.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
- Crews will begin underground utility work.
- Crews will begin constructing curb, gutter, and roadway surfaces.
Week of June 16:
- Crews will work on underground utilities.
- Crews will continue constructing roadway surfaces.
Week of June 9:
- Crews will continue sawcutting and removal of concrete.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
- Crews will work on underground utilities.
- Crews will begin to grade surfaces in preparation for concrete work.
Week of June 16:
- Crews will construct curb, gutter, sidewalk, and roadway surfaces.
Week of June 9:
- Crews will work on underground utilities.
- Crews will grade surfaces in preparation for concrete work.
Week of June 16:
- Crews will continue grading surfaces.
- Crews will construct roadway surfaces and sidewalks.
Week of June 9:
- Crews will work on underground utilities.
- Crews will construct roadway surfaces and sidewalks.
Week of June 16:
- Crews will construct roadway surfaces and sidewalks.
- Crews will stripe the roadway and finish site cleanup.
- Crews will remove traffic control.
Week of June 9:
- Crews will construct new roadway surfaces and sidewalks.
Week of June 16:
- Crews will continue to construct new roadway surfaces and sidewalks.
- Crews will shift work to the north side of the intersection.
- Crews will begin sawcutting and removal of concrete on the north side of the intersection.
- This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Following the completion of civil construction, work is focused on installation of lighting and E Line platform amenities. We will update this section when we have timelines for this work.
Note: The City of Edina is currently constructing sidewalks along the east side of France Avenue between 60th and 62nd streets. This is not METRO E Line work. To learn more about this project or if you have a concern, please reach out to Chad Millner at the City of Edina.
Following the completion of civil construction, work will be focused on installation of E Line platform amenities. We will update this section when we have timelines for this work.
Note: The City of Edina is currently reconstructing 65th Street east of Drew Avenue. This is not METRO E Line work. To learn more about this project or if you have a concern, please see the City’s project website.
- Access to Southdale Hospital and Southdale Medical Center parking lots and garages will be maintained during construction.
- France Avenue can be accessed from the Hospital and Medical Center by taking Drew Avenue to 66th Street.
Week of June 9:
- Crews will finish constructing roadway and sidewalk surfaces.
- Crews will stripe the roadway and begin site cleanup.
Week of June 16:
- Crews will stripe the roadway and finish site cleanup.
- Crews will remove traffic control.
|