|
https://content.govdelivery.com/accounts/MNORGMETC/bulletins/3c6d467
|
|
If you were forwarded this email, subscribe to get all the latest.
UPDATE: The France Avenue detour along Xerxes Avenue has ended. To complete civil construction at France & 54th Street, a short detour was established on Monday, directing northbound traffic to Xerxes, and is anticipated to be removed the week of December 9.
Dates are approximate and subject to change. More details about construction detours and signage will be made available as construction progresses.
Week of Dec. 9:
- Civil construction continues with sidewalk construction.
Week of Dec. 16:
- Civil construction will continue with sidewalk construction.
- Following the completion of civil construction, work is focused on installation of permanent traffic signals and E Line platform amenities. We will update this section when we have timelines for this work.
Week of Dec. 9:
- Electrical cabinet and lighting installation continues.
Week of Dec. 16:
- Electrical cabinet and lighting installation will continue. Following installation, Xcel will complete the final steps of providing power to the electrical cabinet.
Week of Dec. 9:
- Sidewalk construction will continue.
- Electrical cabinet, signal, and lighting installation will begin.
Week of Dec. 16:
- Electrical cabinet, signal, and lighting installation will continue.
- Protective concrete blankets will be removed.
Week of Dec. 9:
- Electrical cabinet, signal, and lighting installation will begin.
- Crews will finish sidewalk construction and remove traffic control.
Week of Dec. 16:
- Electrical cabinet, signal, and lighting installation will continue.
|
|
Final completion of stations will occur next year as Metro Transit prepares for the beginning of E Line service. Activities in 2025 will include installation of station amenities (including shelters, real-time signs, bike racks, and benches) and equipment testing. These activities are expected to take only a few days at each site and will cause minimal disruption to traffic.
Civil construction has also been completed at several stations through coordinated projects with Metro Transit’s partners including:
In addition to stations, E Line construction activities will also include installation of fiber optic communication infrastructure and construction of additional pedestrian, traffic signal, bikeway, and intersection improvements delivered in partnership with Hennepin County and the City of Minneapolis.
- Work in the corridor will include station construction, utility work, pavement and intersection improvements, and traffic signal changes.
- Expect temporary lane restrictions and marked detours for traffic.
- Pedestrian access will remain for businesses and residences.
- Buses will experience detours during construction. Up-to-date information about bus detours and temporary stop locations can be found at metrotransit.org/alerts and by subscription to Rider Alerts.
- Construction will be staged at each station intersection to allow for vehicular traffic flow.
Businesses will remain open during construction, and you can get to know more about local businesses and how to access them during construction through our newsletter! If you would like to have your business featured, email us here.
Any questions about construction can be directed to our construction hotline at 612-524-6050 or to the project email at ELine@metrotransit.org.
More information on the E Line project can be found on the project website.
|
|
|
|