This week, crews installed curb and gutter at Lake & Fremont
Construction is active along Lake Street and Lagoon Avenue in Minneapolis, with major work currently between Excelsior Boulevard and 22nd Avenue.
This week, crews completed the first stage of mill and overlay between Blaisdell and East Bde Maka Ska Parkway on Lake Street and Lagoon Avenue.
The next stage of mill and overlay work will take place in mid-September and will take place between Lake/Excelsior & Market Plaza and Dupont. More information will be shared on this work in the coming weeks.
|
Schedule
-
Crews continue to install underground fiber optic cable along the corridor.
-
Separate from B Line and Lake Street improvements, CenterPoint Energy is updating its infrastructure and gas meters in some locations. CenterPoint Energy staff may contact residents and businesses about potential short-term gas outages as they upgrade equipment. For more information on CenterPoint’s work, view its project website.
Current closure information
-
The right lane of eastbound Excelsior Boulevard and Lake Street between Market Plaza and the Lake Street/Excelsior Boulevard intersection are currently closed, maintaining one lane for through traffic. Both lanes of westbound Excelsior Boulevard are open.
-
The one-way portion of Dean Parkway closed at Lake Street starting Aug. 20.
-
Oakland Avenue is currently closed to the north at Lake Street.
-
The north side of Lake Street between East Bde Maka Ska Parkway and Blaisdell Avenue is currently closed, maintaining one lane for through traffic. Additional traffic control changes may be made near the City of Minneapolis’ 1st Avenue project. Learn more about this project.
-
The north side of Lake Street between 4th and 21st avenues is closed, maintaining one lane in each direction for through traffic. Additional traffic control changes are in place for MnDOT’s Hi-Lake Project on Lake Street east of 21st Avenue. Learn more about this project.
Upcoming construction activities
-
Preparation work for construction of a bus driver restroom facility began this week.
-
Next week, crews will begin utility work at the bus stop area.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Excelsior Boulevard and Market Plaza
-
This week, crews began concrete removals on the concrete median.
-
Next week, crews will begin curb and gutter work.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and West Bde Maka Ska Parkway
-
This week, crews completed concrete removals, conduit crossings, and tree excavations on the north side of the intersection.
-
Next week, crews will begin curb and gutter work as well as bus pad paving.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lagoon and Dupont, Emerson, Fremont, Humboldt, Irving, James, and Knox avenues, E. Bde Maka Ska Parkway
-
Crews will be striping lanes and crosswalks at these intersections in the coming weeks.
-
No additional work is planned at these intersections until later in the year, when crews will return to complete any final finishing and cleanup work.
Lake Street and Knox and James avenues
-
This week, crews completed concrete work at the corners at these intersections.
-
Next week, crews will begin work on the curbs for the protected bike lane.
-
Centerpoint Energy is also working in this area and is expected to restore their construction areas next week.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and Irving, Humboldt, and Holmes avenues
-
This week, crews continued concrete work at the intersection corners and in the bikeway, which will run from Knox Avenue to Humboldt Avenue. This work will continue for two more weeks.
-
Centerpoint Energy is also working in this area and is expected to restore their construction areas next week.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and Fremont and Emerson avenues
-
This week, crews completed hydrant relocations and storm sewer work at Lake and Emerson and completed curb and gutter work at both intersections.
-
Next week, crews will begin underground electrical work and pavement patching at these intersections.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and Lyndale Avenue
-
Mill and overlay work has been completed at this intersection, with striping of lanes and crosswalks to be completed in the coming weeks.
-
No additional work is planned at this intersection until later in the season, when crews will return to complete any final finishing and cleanup work.
Lake Street and Grand Avenue
-
This week, crews completed the new pedestrian median.
-
Mill and overlay work has been completed at this intersection, with striping of lanes and crosswalks to be completed in the coming weeks.
Lake Street and Pillsbury Avenue
-
Mill and overlay work has been completed at this intersection, with striping of lanes and crosswalks to be completed in the coming weeks.
Lake Street and Blaisdell Avenue
-
This week, crews completed the new pedestrian median.
-
Mill and overlay work has been completed at this intersection, with striping of lanes and crosswalks to be completed in the coming weeks.
Lake Street and Portland, Oakland, Park, and Columbus avenues
-
This week, crews completed storm sewer work at Lake & Portland, Lake & Oakland and Lake & Park, and began curb and gutter work at all four intersections.
-
Next week, crews will complete curb and gutter work and pavement patching at the remaining two corners at Park and Portland avenues.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and Chicago Avenue
-
This week, crews completed bus pad paving and pavement patching.
-
Next week, crews will begin underground electrical work and pour concrete for the bus platform.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and Elliot Avenue
-
This week, crews began curb and gutter work.
-
Next week, crews will complete curb and gutter work, pavement patching, and begin underground electrical work.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and 10th, 11th, 12th, and 13th avenues
-
This week, crews completed curb and gutter work at Lake & 10th; completed pavement patching at Lake & 11th, 12th, and 13th; and began underground electrical work at all intersections.
-
Next week, crews will complete underground electrical work.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and 14th Avenue
-
This week, Centerpoint Energy completed work at the intersection and Metro Transit crews began curb and gutter work.
-
Next week, crews will complete curb and gutter work, underground electrical work, and pavement patching at the intersection.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and 15th Avenue
-
This week, crews began underground electrical work.
-
Next week, crews will complete underground electrical work and begin concrete sidewalk work.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and Bloomington Avenue
-
This week, crews began underground electrical work and poured concrete for the bus platform.
-
Next week, crews will complete underground electrical work and begin work on concrete station areas.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and 16th and 17th Avenues
-
This week, crews continued underground electrical work.
-
Next week, crews will complete underground electric work and begin concrete sidewalk work.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Stret and 18th Avenue
-
This week, crews began concrete sidewalk work that will continue for two more weeks.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and Cedar Avenue
-
This week, crews completed underground electrical work, and began work on the concrete station areas and sidewalks.
-
Next week, crews will continue concrete work.
Lake Street and Longfellow, 19th, and 20th avenues
-
This week, crews completed concrete sidewalk work.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
Lake Street and 21st Avenue
-
This week, crews completed underground electrical work, and began concrete sidewalk work that will continue for two more weeks.
-
This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.
|
B Line outreach staff will be at two locations Thursday, Aug. 29, to answer questions and connect with the community.
Midtown Global Market - Main Hall (920 E. Lake St.)
Duet Coffee (1477 W. Lake St.)
While office hours will conclude on Aug. 29, staff are available to attend community events or meetings to connect and answer questions about construction. To have staff visit your next event, contact bline@metrotransit.org
With early morning work and noise now occurring due to mill and overlay work, the B Line project is offering earplugs for neighbors who live near construction and would find them helpful. To receive earplugs, contact bline@metrotransit.org
Any questions about B Line or Lake Street improvements construction can be directed to our construction hotline at 651-356-6995 or to BLine@metrotransit.org.
|