Detour signage for southbound France Avenue is now in place. Phased construction will allow France Avenue to remain open to northbound through traffic for the duration of work, detouring southbound through traffic to Xerxes Avenue between 39th Street and 60th Street. Local traffic between station intersections will be able to travel northbound and southbound.
Traffic control and pedestrian access signage is in place along France Avenue.
Dates are approximate and subject to change. More details about construction detours and signage will be made available as construction progresses.
- This intersection will be fully closed until Metro Transit has completed the subsurface utility work and restored drivable surfaces to the roadway.
- Detours for this construction will follow 39th Street, Xerxes Avenue, and 44th Street.
- Construction will include partial street reconstruction, traffic signal reconstruction, new station platforms, new sidewalk, and new pedestrian ramps.
- Major station construction on the east side of Sheridan Avenue (north of 43rd Street) is scheduled to be complete by the first week of September. Installation of shelters, pylons, and other station features will follow.
- Full two-way traffic is expected to be restored to both sides of Sheridan/Upton by late September/early October.
- Sidewalks will remain open on at least one side of the street and pedestrian access will be maintained to homes and businesses.
Week of Aug. 12:
- Construction continues with adjusting traffic control, underground infrastructure, storm structures and catch basins, and curb construction.
- We anticipate opening northbound traffic on Upton/Sheridan on Friday August 16th (weather depending).
Week of Aug. 19:
- Construction will continue with grading, curb construction, and roadway paving.
Week of Aug. 12:
- Construction crews will continue with construction behind the curb including new platform pavement and sidewalks.
Week of Aug. 19:
- Traffic control will be adjusted to shift work to the east side of France avenue and work will start on removals of pavement and curbs on the northeast corner.
|
|
Week of Aug. 12:
- Construction continues on the east side of France Avenue with grading, road and curb construction on the northeast corner
Week of Aug. 19:
- Construction will continue on the east side of France Avenue with construction of any remaining curbs and sidewalks
Week of Aug. 12:
- Construction continues on the east side of France Avenue with utility and underground electrical work and preparation for platform and sidewalk pavement
Week of Aug. 19:
- Construction will continue on the east side of France Avenue with utility work and construction of the shelter foundation and sidewalks.
Week of Aug. 12:
- Construction continues on the west side of France Avenue with underground utility work, and concrete curb ramp construction on the northwest corner.
- 50th Street Pedestrian Circulation:(MAP)
Week of Aug. 19:
- Construction will continue on the west side of France Avenue with concrete bus pad and curb construction.
Week of Aug. 12:
- Construction continues on the west side of France Avenue with demolition and pavement removals, and underground utility and electrical work.
Week of Aug. 19:
- Construction will continue on the west side of France Avenue with demolition and pavement removals, and apron repair.
These dates are approximate and subject to change. More details about construction detours and signage will be made available as construction gets closer.
Construction work on several additional stations will begin this summer and fall including:
- France & 62nd Street
- Sheridan & 39th Street
- 44th Street & Abbott
- Fairview Southdale Hospital
-
Hennepin & 33rd Street
- Hennepin & 36th Street
Several stations will also be constructed in 2024 through coordinated projects with Metro Transit’s partners including:
In addition to stations, E Line construction activities will also include installation of fiber optic communication infrastructure and construction of additional pedestrian, traffic signal, bikeway, and intersection improvements delivered in partnership with Hennepin County and the City of Minneapolis.
- Work in the corridor will include station construction, utility work, pavement and intersection improvements, and traffic signal changes.
- Expect temporary lane restrictions and marked detours for traffic.
- Pedestrian access will remain for businesses and residences.
- Buses will experience detours during construction. Up-to-date information about bus detours and temporary stop locations can be found at metrotransit.org/alerts and by subscription to Rider Alerts.
- Southbound Route 6 buses will be detoured off France Avenue during E Line Construction.
- Route 46 buses will be detoured off 50th Street between Ewing Avenue and Halifax Avenue.
- See a detour map for affected routes.
- Construction will be staged at each station intersection to allow for vehicular traffic flow.
Come to speak with the METRO E Line Outreach Coordinator in person at:
Càphin Minneapolis 4503 France Ave S, Minneapolis, MN 55410 Wednesday, August 7 from 12:30pm- 2:30pm
Businesses will remain open during construction, and you can get to know more about local businesses and how to access them during construction through our newsletter! If you would like to have your business featured, email us here.
Any questions about construction can be directed to our construction hotline at 612-524-6050 or to the project email at ELine@metrotransit.org.
More information on the E Line project can be found on the project website.
METRO E Line staff will hold office hours at: Jones Coffee - Linden Hills 2814 W 43rd St, Minneapolis, MN 55410 12:30-2:30pm Wednesday July 14.
Stop by to ask questions about the E Line project.
|
|
|
|