Detour signage for southbound France Avenue is now in place. Phased construction will allow France Avenue to remain open to northbound through traffic for the duration of work, detouring southbound through traffic to Xerxes Avenue between 39th Street and 60th Street. Local traffic between station intersections will be able to travel northbound and southbound.
Traffic control and pedestrian access signage is in place along France Avenue, and the installation of temporary traffic signals is occurring along the France Avenue corridor.
|
- Construction is being coordinated with the City of Minneapolis, which is leading an active sewer and water project at this intersection.
- This intersection will be fully closed during city construction and will open to traffic on Upton/Sheridan avenues after the city finishes its project, and while Metro Transit continues construction of E Line platforms.
- Detours for this construction will follow 39th Street, Xerxes Avenue, and 44th Street.
- Construction will include partial street reconstruction, traffic signal reconstruction, new station platforms, new sidewalk, and new pedestrian ramps.
- Major station construction is scheduled to be complete by late-August. Installation of shelters, pylons, and other station features will follow.
- Sidewalks will remain open on at least one side of the street and pedestrian access will be maintained to homes and businesses.
Week of June 24:
- Construction will continue on the west side of France Avenue with underground storm sewer, underground electrical, and concrete work.
- Construction will include partial street reconstruction, new station platforms, new sidewalk, and new pedestrian ramps.
- 58th Street is planned to remain open to through vehicles.
Week of July 1:
- Construction will continue on the west side of France Avenue with construction of curbs, sidewalks, and pedestrian ramps.
|
|
Week of June 24:
- Stage 1 of construction will continue on the east side of France Avenue with utility, underground electrical, and concrete work.
Week of July 1:
- Construction will continue on the east side of France Avenue with construction of curbs, sidewalks, and pedestrian ramps.
Week of June 24:
- Prior to Stage 1 of construction, work on the signal systems continues. Work will include removal of the existing signal poles and installation of a temporary signal system as well as other preparatory activities for station construction.
Week of July 1:
- Following installation of a temporary signal system, Stage 1 of construction is now planned to begin on the east side of France Avenue with pavement removals and demolition work. During the first stage of construction, 44th Street will be closed to through traffic on the east side of France Avenue, with vehicles detoured along Sunnyside Avenue and Grimes Avenue.
- 44th Street Pedestrian Circulation (MAP).
Week of June 24:
- Prior to Stage 1 of construction, work on the signal systems continues. Work will include removal of the existing signal poles and installation of a temporary signal system.
Week of July 1:
- Work on the signal systems will continue. Work will include removal of the existing signal poles and installation of a temporary signal system as well as other activities to prepare for station construction.
Week of July 8:
- Stage 1 of construction is planned to begin on the west side of France Avenue with pavement removals and demolition work. During the first stage of construction, 50th Street will be closed to through vehicles on the west side of France Avenue, with vehicles detoured along Halifax and 51st Street (eastbound) and Market Street (westbound). Trucks will detour around the area via Wooddale Avenue, 58th Street, and Xerxes Avenue.
- 50th Street Pedestrian Circulation: (MAP)
Week of June 24:
- Prior to Stage 1 of construction, work on the signal systems is underway. Work includes removal of the existing signal poles and installation of a temporary signal system.
Week of July 1:
- Work will include removal of the existing signal poles and installation of a temporary signal system as well as other activities to prepare for station construction.
Week of July 8:
- Stage 1 of construction is planned to begin on the west side of France Avenue with pavement removals and demolition work. 54th Street is planned to remain open to through vehicles.
These dates are approximate and subject to change. More details about construction detours and signage will be made available as construction gets closer.
Construction work on several additional stations will begin this summer and fall including:
- France & 62nd Street
- Sheridan & 39th Street
- 44th Street & Abbott
- Fairview Southdale Hospital
-
Hennepin & 33rd Street
- Hennepin & 36th Street
Several stations will also be constructed in 2024 through coordinated projects with Metro Transit’s partners including:
In addition to stations, E Line construction activities will also include installation of fiber optic communication infrastructure and construction of additional pedestrian, traffic signal, bikeway, and intersection improvements delivered in partnership with Hennepin County and the City of Minneapolis.
- Work in the corridor will include station construction, utility work, pavement and intersection improvements, and traffic signal changes.
- Expect temporary lane restrictions and marked detours for traffic.
- Pedestrian access will remain for businesses and residences.
- Buses will experience detours during construction. Up-to-date information about bus detours and temporary stop locations can be found at metrotransit.org/alerts and by subscription to Rider Alerts.
- Southbound Route 6 buses will be detoured off of France Avenue during e Line Construction. (MAP)
- Construction will be staged at each station intersection to allow for vehicular traffic flow.
Businesses will remain open during construction, and you can get to know more about local businesses and how to access them during construction through our newsletter! If you would like to have your business featured, email us here.
Any questions about construction can be directed to our construction hotline at 612-524-6050 or to the project email at ELine@metrotransit.org.
More information on the E Line project can be found on the project website.
|
|
|
|