Newly installed B Line shelters at Selby & Dale
METRO B Line shelter installations continue
Over the next two weeks, shelter installations will occur at Marshall & Otis, Lake & 44th, and Lake & 36th
-
Shelter installations require the use of a small crane in the sidewalk/parking area and are usually completed within one working day. No road closures are needed.
-
Crews will be on site to detour traffic or pedestrians for any temporary impacts to sidewalks or travel lanes
-
Shelter installations are not as loud as other forms of construction activities, but may have sounds of drilling, crews communicating, and large vehicle noises
-
Shelters will not be available for customer use immediately upon installation and will be fenced off. Crews will need to complete several tasks to ensure shelters are safe and ready for regular route service. Shelters are expected to be available for customer use later this year.
|
Crews have started to paint the red bus-only lane on Lake Street
Minneapolis
Ongoing
This week, crews continued work on painting the bus-only lane and wiring for the traffic signal system.
Upcoming
Over the next few weeks, crews will be out along the corridor doing finishing tasks including sod placement, light concrete work, applying sealant to platform areas, signal wiring, cleaning work areas, and removing traffic control items.
Station construction continues at Selby & Western
Selby & Western
-
Work began on the northeast corner of the intersection the week of October 2. Selby Avenue is currently closed to vehicle traffic on the east side of the intersection for a half of a block between Western and Virginia
-
Traffic and transit are directed to detour onto Dayton Avenue between Arundel Street. and Farrington Street
-
Construction will include partial street reconstruction, new station platforms, new street, new sidewalk, new pedestrian ramps
-
This week, crews completed electrical work and poured the concrete bus pad
-
Next week, crews will begin work on the concrete station areas
Roadway & sidewalk construction activities are complete at these locations
Crews have completed all pavement work at these stations and the intersections are fully re-opened to traffic.
-
Marshall & Otis
-
Marshall & Cretin
-
Marshall & Cleveland
-
Marshall & Fairview
-
Selby & Hamline
-
Selby & Lexington
-
Selby & Victoria
-
Selby & Dale
-
Selby & Arundel
-
John Ireland & Marshall
Some stops may still be temporarily closed at some intersections along the corridor. Please use the nearest stops to these intersections.
Any questions about construction can be directed to our construction hotline at 651-356-6995 or to the project email at BLine@metrotransit.org.
More information on the B Line project can be found on the project website.
|
|
|
|