Construction at these intersections began May 15. Expect the following activities:
Marshall & Cleveland
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work, then transition to installation of station features. The intersection will be open to four-way traffic, with lane restrictions along Marshall Avenue.
-
Crews completed the northern half of the station area, and have shifted work and traffic control to the south side of Marshall Avenue
-
Crews have completed concrete removals and storm sewer work on the southeast corner of the intersection.
-
Crews will begin work on fiber optic cable and on concrete station areas.
-
All pavement work is anticipated to be completed in mid-July.
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
Marshall & Fairview
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work then transition to installation of station features. The intersection will be open to four-way traffic, with lane restrictions along Marshall Avenue.
-
Crews completed the northern half of the station area, and have shifted work and traffic control to the south side of Marshall Avenue
-
Crews have completed concrete removals and fiber optic cable work on the southeast corner of the intersection.
-
Crews will begin work on the concrete station areas.
-
All pavement work is anticipated to be completed in mid-July.
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
Selby & Lexington
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work then transition to installation of station features. Selby Avenue is currently closed to vehicle access on the east side of the intersection for 30 working days, with a projected reopening in late June.
Traffic and transit detours are routed to Marshall Avenue between Hamline Avenue and Victoria Street. Local access will be maintained for residents and businesses between Hamline and Victoria along Selby Avenue.
-
Crews are completing electrical work and concrete station work
-
Crews will complete pavement station areas.
-
All pavement work is anticipated to be completed and the intersection will be reopened by June 30.
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
Construction at these intersections began June 5. Expect the following activities:
Lake Street
Station construction along Lake Street between Minnehaha Avenue and the Mississippi River started the week of June 5 and is moving from east to west. This includes stations at Lake & Minnehaha, Lake & 31st Avenue, Lake & 36th Avenue, and Lake & 44th Avenue.
Construction work and a full lane closure will begin first on the northern half of the street and will move east to west starting at Lake Street & West River Parkway. Work is expected to move to the south side of Lake Street in late July. Two-way traffic will be maintained along Lake Street throughout construction, with lane restrictions in place.
Construction at station locations includes partial street reconstruction, new station platforms, new street, new sidewalk, new traffic signals, and new pedestrian ramps.
Construction at non-station intersections will include curb ramp work, new sidewalk, roadway improvements, and signal improvements.
Later this summer, construction will include a mill and overlay as well as lane restriping. Sidewalks will remain open on at least one side of the street and pedestrian access will be maintained to homes and businesses.
Crews are working on pavement and curb and gutter work on the northern half of the street at:
-
Lake & West River Parkway (complete by June 27)
-
Lake & 47th (complete by June 27)
-
Lake & 45th (complete by June 27)
-
Lake & 44th (complete mid-late July)
-
Lake & 43rd (complete by June 30)
-
Lake & 42nd (complete by June 30)
-
Lake & 36th (complete by mid-late July)
Crews are completing electrical and pavement work at Lake & 39th. The north leg of the intersection is closed to traffic due to the need for storm sewer work until June 23. Work at this intersection will be complete by July 6.
Crews have begun work on curb and gutter as well as bus pad paving at Lake & 36th and at Lake & 44th.
Crews will complete pavement work next week on the north side of the street at Lake & West River Parkway, Lake & 47th, Lake & 45th, Lake & 44th, Lake & 43rd, and Lake & 42nd.
Electrical work and concrete station work will begin at Lake & 36th and Lake & 44th.
Pavement removals will begin next week at Lake & 33rd, Lake & 31st, Lake & 27th, and Lake & Minnehaha.
View plans for construction on Lake Street
Roadway & sidewalk construction activities are complete at these locations
Crews have completed all pavement work at these stations and the intersections are re-opened to traffic.
-
Selby & Hamline
-
Selby & Victoria
-
John Ireland & Marshall
The installation of shelters, pylons, and other station features will follow, with all major work scheduled to be complete by late August.