Concrete station work continues at Selby & Hamline
Construction at these intersections began May 15. Expect the following activities:
Marshall & Cleveland
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work, then transition to installation of station features. The intersection will be open to four-way traffic, with lane restrictions along Marshall Avenue.
-
Crews are completing pavement work on the shelter area. This work will continue into next week
-
Pavement and electrical work is expected to transition to the southeast corner of the intersection by the end of next week. Pavement removals will begin on the week of June 19
-
All pavement work is anticipated to be completed in mid-July
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
Marshall & Fairview
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work then transition to installation of station features. The intersection will be open to four-way traffic, with lane restrictions along Marshall Avenue.
-
Crews are completing pavement work on the shelter area. This work will continue into next week
-
Pavement and electrical work is expected to transition to the southeast corner the intersection by the end of next week. Pavement removals will begin on the week of June 19
-
All pavement work is anticipated to be completed in mid-July
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
Selby & Hamline
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work then transition to installation of station features. Selby Avenue is currently closed to vehicle access on the east side of the intersection for 30 working days, with a projected reopening in late June.
Traffic and transit detours are routed to Marshall Avenue between Hamline Avenue and Victoria Street. Local access will be maintained for residents and businesses between Hamline and Victoria along Selby Avenue.
-
Crews are finishing electrical work and beginning to work on the pavement station areas
-
Crews will finish pavement station areas
-
All pavement work is anticipated to be completed by late June
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
Selby & Lexington
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work then transition to installation of station features. Selby Avenue is currently closed to vehicle access on the east side of the intersection for 30 working days, with a projected reopening in late June.
Traffic and transit detours are routed to Marshall Avenue between Hamline Avenue and Victoria Street. Local access will be maintained for residents and businesses between Hamline and Victoria along Selby Avenue.
-
Crews are completing utility, storm sewer, and fiber optic installation work
-
Crews will soon begin work on curb and gutter as well as pavement station areas
-
All pavement work is anticipated to be completed by late June
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
Selby & Victoria
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction activities will first include street and sidewalk work then transition to installation of station features. Selby Avenue is currently closed to vehicle access on the west side of the intersection for 30 working days, with a projected reopening in late June.
Traffic and transit detours are routed to Marshall Avenue between Hamline Avenue and Victoria Street. Local access will be maintained for residents and businesses between Hamline and Victoria along Selby Avenue.
-
Crews are completing curb and gutter work as well as bus pad paving
-
Crews will begin electrical work and work on the pavement station areas.
-
All pavement work is anticipated to be completed by late June
The installation of shelters, pylons, and other station features will follow shortly thereafter at both the north and south sections of the intersection, with all major work scheduled to be complete by late August.
The community between construction areas at Selby & Lexington and Selby & Victoria has experienced several water outages in the past weeks. While the B Line project did have planned water work at Selby and Lexington in late May, there has been additional emergency work needed as water main valves broke and began leaking due to old age.
Work that was supposed to be concentrated in a residential area around Lexington had to be expanded quickly to resolve the issue, affecting a larger range of water customers. Saint Paul Regional Water Service is coordinating this work and can be reached by phone at 651-266-6350.
John Ireland & Marshall
Construction at this intersection will include new station platforms and partial street reconstruction featuring new street, sidewalk, and pedestrian ramps.
Construction has progressed ahead of schedule at this station, and John Ireland Boulevard re-opened to vehicle traffic this week.
-
Crews have completed all pavement work at the station
-
Installation of shelters, pylons, and other features
-
All station work is anticipated to be completed by late August
Lake Street
-
Construction work on Lake Street between Minnehaha Avenue and the Mississippi River started this week and will move from east to west along Lake Street. This includes station construction at Lake & Minnehaha, Lake & 31st Avenue, Lake & 36th Avenue, and Lake & 44th Avenue.
-
Work will begin first on the northern half of the street and will move east to west starting at Lake Street & Mississippi River Boulevard. Two-way traffic will be maintained along Lake Street and will move to the south side of the intersection, with lane restrictions in place.
-
Construction at station locations includes partial street reconstruction, new station platforms, new street, new sidewalk, new traffic signals, and new pedestrian ramps.
-
Construction at non-station intersections will include curb ramp work, new sidewalk, roadway improvements, and signal improvements. Later this summer, construction will include a mill and overlay as well as lane restriping.
-
Sidewalks will remain open on at least one side of the street and pedestrian access will be maintained to homes and businesses.
-
Crews have started to prep several intersections for upcoming construction
-
Temporary traffic signals have been installed
-
Pavement removals and curb and gutter work have started at Lake & West River Parkway, Lake & 47th, and Lake & 45th
-
Crews will continue pavement work at Lake & West River Parkway, Lake & 47th, Lake & 45th
-
Pavement removals and curb and gutter work will begin at Lake & 43rd, Lake & 42nd, Lake & 39th, and Lake & 36th
View plans for construction on Lake Street
|
|
Construction work on several additional St. Paul stations will begin in July including Marshall & Otis, Marshall & Cretin, Selby & Dale, and Selby & Arundel.
Transit detours will be in place until late August. These detours include:
-
Route 21 buses are detoured off Selby Avenue onto Marshall Avenue between Hamline Avenue and John Ireland Boulevard.
-
Stops in both directions are closed at Marshall Avenue & Cleveland Avenue and at Marshall Avenue & Fairview Avenue. Please use either of the nearest stops to the east or west of these intersections
-
Please see metrotransit.org/rider-alerts to sign up for Rider Alerts, view new stop locations, and learn more about Route 21 detours.
Metro Transit Outreach staff will be available at two locations weekly on Thursdays for walk-in conversations and to answer questions about construction.
12:30-2:00 p.m. at Dogwood Coffee (4021 E. Lake St., Minneapolis)
2:15-3:45 p.m. at Golden Thyme Coffee & Café (934 Selby Ave., St. Paul)
Any questions about construction can be directed to our construction hotline at 651-356-6995 or to the project email at BLine@metrotransit.org
More information on the B Line project can be found on the project website
|