Stations are being installed at locations where significant construction was completed last year, such as Fremont & 42nd Ave
Five stations are planned for construction in 2022. Construction work began on April 18 and will continue throughout the year. Weekly updates tracking the start of construction at the remaining stations and general construction progress will continue as this year’s construction season occurs.
-
Construction at this intersection started the week of April 18.
-
The intersection will be fully closed for one month, with 2-3 months of lane restrictions following closure.
-
Construction will include new station platforms, shelter and pylon installation, partial street reconstruction, street pavement, sidewalk, pedestrian ramps, signals, and utility work.
-
The week of May 2, crews continued work on water and storm sewers. Next week, crews will begin curb and gutter work and pour concrete for bus pads.
-
Construction at this intersection started the week of April 18.
-
The intersection will be fully closed for one month, with 2-3 months of lane restrictions following closure.
-
Construction will include new station platforms, shelter and pylon installation, street pavement, sidewalk, pedestrian ramps, signals, and utility work.
- The week of May 2, crews completed paving and concrete work and begin electrical work. Next week, electrical work will continue alongside work on the concrete station areas.
-
Construction at this intersection started the week of April 25.
-
The intersection will be partially closed for 3-4 months, with lane restrictions in place.
-
Construction will include new station platforms, shelter and pylon installation, sidewalk, pedestrian ramps, signals, and utility work.
- The week of May 2, crews completed storm and water system work. Next week, crews will begin concrete curb and gutter work.
-
Construction at this intersection started the week of May 2.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include new station platforms, shelter and pylon installation, sidewalk, pedestrian ramps, signals, and utility work.
-
The week of May 2, crews began concrete removals. Next week, crews will begin water and storm sewer work.
-
Construction at this intersection is planned to start later in spring.
-
The intersection will be partially closed for 2-3 months, with lane restrictions in place.
-
Construction will include new station platforms, shelter and pylon installation, sidewalk, pedestrian ramps, signals, and utility work.
|