A map showing completed and scheduled D Line construction work
Five stations are planned for construction in 2022. Work is currently planned to begin on some stations as early as April 18 if weather allows. Weekly updates tracking the start of construction at the remaining stations and general construction progress will resume as this year’s construction season begins.
-
Construction at this intersection is planned to start the week of April 18, with materials to arrive at the intersection the week of April 11.
-
The intersection will be fully closed for one month, with 2-3 months of lane restrictions following closure.
-
Construction will include new station platforms, shelter and pylon installation, partial street reconstruction, street pavement, sidewalk, pedestrian ramps, signals, and utility work.
- The week of April 18, crews will begin removing concrete and start water work.
-
Construction at this intersection is planned to start the week of April 18, with materials to arrive at the intersection the week of April 11.
-
The intersection will be fully closed for one month, with 2-3 months of lane restrictions following closure.
- Construction will include new station platforms, shelter and pylon installation, street pavement, sidewalk, pedestrian ramps, signals, and utility work.
-
The week of April 18, crews will begin removing concrete and start water work.
-
Construction at this intersection is planned to start the week of April 25, weather permitting.
-
The intersection will be partially closed for 3-4 months, with lane restrictions in place.
- Construction will include new station platforms, shelter and pylon installation, sidewalk, pedestrian ramps, signals, and utility work.
-
Construction at this intersection is planned to start the week of May 2, weather permitting.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include new station platforms, shelter and pylon installation, sidewalk, pedestrian ramps, signals, and utility work.
7th St. & Olson/5th Ave.
-
Construction at this intersection is planned to start later in spring.
-
The intersection will be partially closed for 2-3 months, with lane restrictions in place.
- Construction will include new station platforms, shelter and pylon installation, sidewalk, pedestrian ramps, signals, and utility work.
|
Crews have continued to install shelters and other station amenities at D Line station locations where foundations were completed last year. Crews are starting on the north end of the line and moving south as shelters are installed. While station areas will still be open for customer use, the shelter areas will not be able to be used until later this year, while electrical work, testing, and safety certifications are still ongoing.
Additionally, route testing has begun for D Line buses and service. Metro Transit staff are currently running test buses along the D Line to begin testing schedules for the future service.