An updated construction map showing completed D Line construction work
During the 2021 construction season, crews were able to complete street construction, station foundation, and underground work on 25 of the 30 future D Line stations. Five of these stations were completed ahead of schedule, significantly reducing the amount of construction work to begin next year.
During the next few weeks, you’ll see crews preparing the station areas for winter. D Line shelters and other station amenities will be installed next year, with construction and installation of all stations completed in time to prepare for D Line service starting at the end of 2022.
As space allows at bus stops with high ridership, temporary bus shelters will be installed near future D Line stations to protect customers from inclement weather this winter.
Stations planned for 2022 construction
Five stations are planned for construction in 2022. Timelines for construction start will be determined in late winter, but work is currently planned to begin as early as April if weather allows.
-
The intersection will be partially closed for 2-3 months, with lane restrictions in place.
-
Construction will include new station platforms, sidewalk, pedestrian ramps, signals, and utility work.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include new station platforms, sidewalk, pedestrian ramps, signals, and utility work.
-
The intersection will be partially closed for 3-4 months, with lane restrictions in place.
-
Construction will include new station platforms, sidewalk, pedestrian ramps, signals, and utility work.
-
The intersection will be fully closed for one month, with 2-3 months of lane restrictions following closure.
-
Construction will include new station platforms, street pavement, sidewalk, pedestrian ramps, signals, and utility work.
-
The intersection will be fully closed for one month, with 2-3 months of lane restrictions following closure.
- Construction will include new station platforms, partial street reconstruction, street pavement, sidewalk, pedestrian ramps, signals, and utility work.
|
Completed METRO D Line station foundations at 42nd and Fremont Ave. in North Minneapolis
Construction updates will resume in 2022
As major construction has been completed for the season, updates will pause for the winter and will resume in March as we prepare for the next season of construction.
Route 5 detours complete for the year, will resume in 2022
All Metro Transit construction-related detours are complete for the year. Stops along 44th Avenue in North Minneapolis are currently still detoured to 43rd Avenue until completion of the current phase of the Webber 44 project.
Route 5 buses remain on indefinite detour off Chicago Ave. onto Park Ave. and Portland Ave. from 36th St. to 42nd St.
Up-to-date information can be found at metrotransit.org/alerts. Subscribe to Rider Alerts for up-to-date information. Experiencing construction issues? Please connect with our construction hotline at 612-568-1038.