Landscaping work begins at a nearly finished station platform at 7th & Bryant.
Construction on five new intersections will begin soon:
Dates below are forecasts, and are subject to change based on weather and unforeseen conditions
Emerson/Fremont & Broadway
-
Construction will begin next week.
-
The intersection will be partially closed for 3-4 months, with lane restrictions in place.
-
Construction will include station platforms, new pedestrian ramps, new signals and sidewalks, street pavement, and utility work.
-
Construction will begin the week of June 21.
-
The intersection will be partially closed for 3-4 months, with lane restrictions in place.
-
Construction will include station platforms, new pedestrian ramps, new signals and sidewalks, street pavement, and utility work.
-
Construction will begin the week of July 5.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include station platforms, new pedestrian ramps, new signals and sidewalks, street pavement, and utility work.
-
Construction will begin the week of July 5.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include station platforms, new pedestrian ramps, new signals and sidewalks, street pavement, and utility work.
-
Construction will begin the week of July 5.
-
The intersection will be partially closed for up to six months, with lane restrictions in place.
-
Construction will include station platforms, new pedestrian ramps, a new pedestrian crosswalk and refuge island, new signals and sidewalks, street pavement, and utility work.
|
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Intersections partially closed April 15, with lane closures in place for up to four months.
-
This week, crews continued work on the concrete shelter areas and on landscaping. This work will continue into next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Also included will be removal of the median on Aldrich Ave. N., and construction of a single inlet/outlet on Aldrich Ave. N. to and from N. 7th St., traveling southbound. Work also includes reconstruction and realignment of the northern sidewalk adjacent to Aldrich Ave., and installation of a new traffic signal at N. 7th St.
-
Construction began April 5 and will continue for up to three months, with lane closures in place. Lane closures will end on June 11.
-
Most major construction work is complete at this intersection. Some light finishing work may be needed before lane closures end.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection has reopened from full closure and will have lane closures in place for up to two months.
-
This week, crews worked on lane striping. This work will continue into next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, partial street reconstruction, new pedestrian ramps, signals, and sidewalks.
-
Also included will be partial street reconstruction, new pedestrian ramps, and sidewalks at all three corners of Franklin and Columbus.
-
The intersection has reopened from full closure and will have lane closures in place for up to four months.
-
This week, crews began shelter concrete work. This work will continue into next week alongside landscaping work.
Chicago-Lake Transit Center
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, street reconstruction, new pedestrian ramps, signals, and sidewalks. Also included will be a realignment of the bus-only lane from the center of Chicago Ave. to the curbside lane.
-
The intersection partially closed the week of April 23, with lane closures in place for up to four months.
-
This week crews began water work, storm sewer work, and fiber work. Water and storm sewer work will continue into next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection reopened to vehicle traffic May 20. Lane closures will continue for up to three months.
-
Most major construction work is complete at this intersection. Some light finishing work may be needed before lane closures end.
-
Construction includes station platforms, new sidewalk, new pedestrian signals and ramps, street pavement, and utility work.
-
The intersection is fully closed to vehicle traffic starting May 19, for up to a month.
-
The intersection will re-open in late June, with up to three months of lane closures following the reopening.
-
This week, crews began electrical work. This work will continue into next week.
-
Construction includes station platforms, a new bike/pedestrian path, new pedestrian ramps, partial driveway reconstruction, street pavement, and utility work. Work will be coordinated with Hennepin County construction happening in the area.
-
The intersection partially closed the week of May 27, with lane restrictions in place for 4-5 months.
-
This week, crews completed curb and gutter work, and began work on concrete station areas. This work will continue into next week.
-
Construction includes station platforms, a new bike/pedestrian path, new pedestrian ramps, street pavement, and utility work.
-
The intersection partially closed the week of May 27, with lane restrictions in place for 4-5 months.
-
This week, crews completed curb and gutter work, and began work on concrete station areas. This work will continue into next week.
-
Construction includes station platforms, a new bike/pedestrian path, new pedestrian ramps, street pavement, and utility work.
-
The intersection partially closed the week of May 27, with lane restrictions in place for 4-5 months.
-
This week, crews completed curb and gutter work, and began work on concrete station areas. This work will continue into next week.
-
Construction will include temporary station platforms, a new bike/pedestrian path, new pedestrian ramps, street pavement, and utility work.
-
The intersection partially closed the week of May 27, with lane restrictions in place for 4-5 months.
-
This week, crews began work on concrete station areas. This work will continue into next week.
Major construction has completed at the following stations:
Fremont & Plymouth: Work on Emerson & Plymouth has not started.
Route 5 detours, bus stop closures continue:
All Route 5 service is detoured off Chicago between downtown Minneapolis and 42nd Ave.
Southbound buses will travel on Chicago to 9th St., right on 9th St., left on Portland, left on 42nd St., right on Chicago and resume regular route.
Northbound buses will travel on Chicago to 42nd St., left on 42nd St., right on Park, right on 8th St., left on Chicago, left on 7th St. and resume regular route.
-
All northbound stops on Chicago Ave. between 35th St. E. and 8th St. S.
-
All southbound stops on Chicago Ave. between 14th St. E. and 35th St. E.
Emerson/Fremont and Lowry detour:
-
Northbound buses will travel on Emerson, right on 30th, left on Dupont, left on 33rd and resume regular route.
-
Southbound buses will travel on Fremont to 33rd, left on Girard, left on 30th, right on Fremont and resume regular route.
Route 5 service is detoured off Fremont Ave. between 34th Ave. and 36th Ave.
-
Northbound buses will travel on Fremont to 34th, left on 34th, right on Girard, go north on Girard to 36th, right on 36th, left on Fremont and resume regular route.
-
Southbound buses will travel on Fremont to 36th, right on 36th, left on Girard, go south on Girard to 34th, left on 34th, right on Fremont and resume regular route.
Portland Avenue bus stop closures:
Route 5 stops at Portland Ave. S. & 61st St. E. and Portland Ave. S. & Park Ave. will be closed
-
Customers board buses one block north at 60th St. E.
Route 5 stop at Portland Ave. S. & 62nd St. E. will be closed
-
Customers board buses two blocks south at 64th St. E.
Route 5 stop at Portland Ave. S. & 66th St. E. will be closed
-
Customers board buses two blocks north at 64th St. E. or one block south at 67th St. E.
Route 5 stop at Portland Ave. S. & 70th St. E. will be closed
-
Customers board buses one block north at 69th St. E. or one block south at 71st. St. E.
Route 5 stop at Portland Ave. S. & 73rd St. E. will be closed
-
Customers board buses one block north at 72nd St. E or one block south at 74th St. E.
Route 5 stop at Portland Ave. S. & 77th St. E. will be closed
-
Customers board buses one block north at 76th St. E.
Up-to-date information can be found at metrotransit.org/alerts. Subscribe to Rider Alerts for up-to-date information.
More information
|