an electrical handhole at Chicago Ave. & Franklin
Construction at five more intersections will begin in May:
Dates below are forecasts, and are subject to change based on weather and unforeseen conditions
-
Construction will begin next week.
-
The intersection will be fully closed to vehicle traffic starting Tuesday, May 18 for up to a month.
-
The intersection will re-open in late June, with up to three months of lane closures following the reopening.
-
Construction will include station platforms, new sidewalk, new pedestrian signals and ramps, street pavement, and utility work.
-
Construction will begin the week of May 27. Work will be coordinated with Hennepin County construction happening in the area.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include station platforms, a new bike/pedestrian path, new pedestrian ramps, partial driveway reconstruction, street pavement, and utility work.
-
Construction will begin the week of May 27.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include station platforms, modifications to sidewalks and bike/pedestrian paths, new pedestrian ramps, and utility work.
-
Construction will begin the week of May 27.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include station platforms, modifications to sidewalks and bike/pedestrian paths, new pedestrian ramps, and utility work.
-
Construction will begin the week of May 27.
-
The intersection will be partially closed for 4-5 months, with lane restrictions in place.
-
Construction will include temporary BRT stations and concrete work.
|
-
Construction will include station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersections were partially closed April 15, with lane closures in place for up to four months. The full closure of Fremont & Lowry is expected to end next week.
-
This week, crews completed electrical work, and began work on curb and gutters and platform areas. Next week, curb and gutter and platform work will continue.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Construction began on April 8 and will continue for up to three months, with lane closures in place.
-
This week, crews finished the shelter area as well as landscaping near the shelter. Next week, lane striping will occur.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Also included will be removal of the median on Aldrich Ave. N., and construction of a single inlet/outlet on Aldrich Ave. N. to and from N. 7th St., traveling southbound. Work also includes reconstruction and realignment of the northern sidewalk adjacent to Aldrich Ave., and installation of a new traffic signal at N. 7th St.
-
Construction began on April 5 and will continue for up to three months, with lane closures in place.
-
This week, crews began work on the shelter area and landscaping. Next week, work on the shelter areas and landscaping will continue.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection has reopened from full closure and will have lane closures in place for up to two months.
-
This week, crews began work on the shelter area and shelter seat walls. This work will continue into next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, partial street reconstruction, new pedestrian ramps, signals, and sidewalks.
-
Also included will be partial street reconstruction, new pedestrian ramps, and sidewalks at all three corners of Franklin and Columbus.
-
The intersection has reopened from full closure and will have lane closures in place for up to four months.
-
This week, crews completed storm sewer work. Next week, bus pad paving and signal installation will occur.
Chicago-Lake Transit Center
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, street reconstruction, new pedestrian ramps, signals, and sidewalks. Also included will be a realignment of the bus-only lane from the center of Chicago Ave. to the curbside lane.
-
The intersection was partially closed the week of April 23, with lane closures in place for up to four months.
-
This week, crews completed electrical work. Next week, crews will begin pouring concrete for station platforms and walls.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection was fully closed to vehicle traffic on April 12.
-
The intersection will reopen to vehicle traffic next week with up to three months of lane closures following the reopening.
-
This week, crews completed electrical work. Next week, crews will begin pouring concrete for station platforms and walls.
All Route 5 service is detoured off of Chicago between downtown Minneapolis and 42nd Ave.
Southbound buses will travel on Chicago to 9th St., right on 9th St., left on Portland, left on 42nd St., right on Chicago and resume regular route.
Northbound buses will travel on Chicago to 42nd St., left on 42nd St., right on Park, right on 8th St., left on Chicago, left on 7th St. and resume regular route.
-
All northbound stops on Chicago Ave between 35th St. E. and 8th St. S.
-
All southbound stops on Chicago Ave between 14th St. E. and 35th St. E.
-
Northbound buses will travel on Emerson, right on 30th, left on Dupont, left on 33rd and resume regular route.
-
Southbound buses will travel on Fremont to 33rd, left on Girard, left on 30th, right on Fremont and resume regular route.
Route 5 service will be detoured off Fremont Avenue between 34th Ave. And 36th Ave. starting on May 19.
Northbound buses will travel on Fremont to 34th , left on 34th, right on Girard, go north on Girard to 36th, right on 36th, left on Fremont and resume regular route.
Southbound buses will travel on Fremont to 36th, right on 36th, left on Girard, go south on Girard to 34th, left on 34th, right on Fremont and resume regular route.
-
Northbound and southbound stops at Fremont Ave. & 35th
|
|