April 15: Concrete removals begin at the Chicago-Lake Transit Center
Emerson/Fremont & Lowry Ave. work will begin the week of April 19:
-
Construction will include station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersections will be partially closed starting April 15, with lane closures in place for up to four months.
-
Lane shifts and construction materials will arrive on April 15. Concrete removals start the week of April 19.
|
|
|
April 15- Crews are completing curb and gutter work at the intersection of Chicago Ave. & Franklin Ave.
Chicago & 14th Street
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection was fully closed April 7 and will be closed for one month. The intersection will be reopened in early May followed by several months of lane closures.
-
Concrete removals have been completed. Utility work and water/hydrant work are underway and will be completed next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, partial street reconstruction, new pedestrian ramps, signals, and sidewalks.
-
Also included will be partial street reconstruction, new pedestrian ramps, and sidewalks at all three corners of Franklin and Columbus.
-
Construction began on April 5 and will continue for approximately six months with lane closures in place.
-
Utility work and curb and gutter placement started this week. Signal work and platform foundation work is scheduled to begin next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Also included will be removal of the median on Aldrich Ave. N., and construction of a single inlet/outlet on Aldrich Ave. N. to and from N. 7th St., traveling southbound. Work also includes reconstruction and realignment of the northern sidewalk adjacent to Aldrich Ave., and installation of a new traffic signal at N. 7th St.
-
Construction began on April 5 and will continue for up to three months, with lane closures in place.
-
Concrete curbs and gutters have been poured. Next week asphalt work will occur along with concrete for the shelter platform.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Construction began on April 8 and will continue for up to three months, with lane closures in place.
-
Concrete removals and underground utility work have been completed. Next week, crews will begin pouring curb and gutters, as well as the concrete bus pads.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection will be fully closed to vehicle traffic starting Monday, April 12 for up to a month.
-
The intersection will reopen to vehicle traffic in mid-May, with up to three months of lane closures following the reopening.
-
This week, crews completed concrete removals and underground cable work. Next week, crews will begin water and sewer work.
Chicago-Lake Transit Center
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, street reconstruction, new pedestrian ramps, signals, and sidewalks. Also included will be a realignment of the bus-only lane from the center of Chicago Avenue to the curbside lane.
-
The intersection will be partially closed starting next week, with lane closures in place for up to four months.
-
This week, crews began concrete removals. Next week, crews will complete the concrete removals and begin underground cable work.
|
All Route 5 service is detoured off of Chicago between downtown Minneapolis and 42nd Ave.
Southbound buses will travel on Chicago to 9th St., right on 9th St., left on Portland, left on 42nd St., right on Chicago and resume regular route.
Northbound buses will travel on Chicago to 42nd St., left on 42nd St., right on Park, right on 8th St., left on Chicago, left on 7th St. and resume regular route.
-
All northbound stops on Chicago Ave between 35th St. E. and 8th St. S.
-
All southbound stops on Chicago Ave between 14th St. E. and 35th St. E.
-
Northbound Emerson shelter (#8935) and southbound Fremont shelter (#11146) will be removed the week of April 18
-
Northbound buses will travel on Emerson, right on 30th, left on Dupont, left on 33rd and resume regular route
-
Southbound buses will travel on Fremont to 33rd, left on Girard, left on 30th, right on Fremont and resume regular route
Signage for planned detours are located throughout the corridor
|
|
|
|
|