April 2: Construction crews prepare temporary traffic signals for construction at Chicago & Franklin
Work will begin at these intersections the week of April 12:
Dates below are forecasts, and are subject to change based on weather and unforeseen conditions.
-
Next week, crews will begin concrete removal in the intersection as well as underground cable work.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection will be fully closed to vehicle traffic starting Monday, April 12 for up to a month.
-
The intersection will reopen in mid-May, with up to three months of lane closures following the reopening.
Chicago-Lake Transit Center
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, street reconstruction, new pedestrian ramps, signals, and sidewalks. Also included will be a realignment of the bus-only lane from the center of Chicago Avenue to the curbside lane.
-
The intersection will be partially closed starting next week, with lane closures in place for up to four months.
-
Next week, crews will begin concrete removals in the intersection.
-
Construction will include station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersections will be partially closed starting April 15, with lane closures in place for up to four months.
- Lane shifts and construction materials will arrive on April 15.
|
Intersections with construction underway
Chicago & 14th Street
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
The intersection was fully closed April 7, and will be closed for one month. The intersection will be reopened in early May followed by several months of lane closures.
-
Concrete removals and utility work have been completed.
-
Water/hydrant work begins next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, new street pavement, partial street reconstruction, new pedestrian ramps, signals, and sidewalks in the opposite non-BRT corners of the intersection.
-
Also included will be partial street reconstruction, new pedestrian ramps, and sidewalks at all three corners of Franklin and Columbus.
-
Construction began on April 5 and will continue for approximately six months with lane closures in place.
-
Concrete removals and underground work have been completed.
-
Utility work, curb and gutter work starts next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Also included will be removal of the median on Aldrich Ave. N., and construction of a single inlet/outlet on Aldrich Ave. N. to and from N. 7th St., traveling southbound. Work also includes reconstruction and realignment of the northern sidewalk adjacent to Aldrich Ave., and installation of a new traffic signal at N. 7th St.
-
Construction began on April 5 and will continue for up to three months, with lane closures in place.
-
Concrete removals and storm sewer work have been completed.
-
Concrete curb will be poured next week.
-
Construction includes station platforms, new sidewalk, new pedestrian signals, utility work, and new street pavement.
-
Construction began on April 8 and will continue for up to three months, with lane closures in place.
-
Concrete removals have been completed.
-
Crews will pour the concrete curbs over the next two weeks.
|
|
Monday, April 12- All Route 5 service will be detoured off of Chicago between downtown Minneapolis and 42nd Ave.
Southbound buses will travel on Chicago to 9th St., right on 9th St., left on Portland, left on 42nd St., right on Chicago and resume regular route.
Northbound buses will travel on Chicago to 42nd St., left on 42nd St., right on Park, right on 8th St., left on Chicago, left on 7th St. and resume regular route.
-
All northbound stops on Chicago Ave between 35th St. E. and 8th St. S.
-
All southbound stops on Chicago Ave between 14th St. E. and 35th St. E.
|
|
|
|
|