TRF Project Update: October 2, 2020
Happy Friday!
RJ Zavoral opened Brooks Avenue at Greenwood Street Thursday evening (10-1-2020) and closed Lowell Drive at Greenwood Street begining at 7:00 A.M. today (Friday, October 2nd) to continue installation of 54” concrete storm sewer. Lowell Drive will be closed at Greenwood Street for approximately five days. Updates will be provided as they become available.
Please allow extra time and use alternate routes when possible.
Project Updates
MnDOT
Hwy 1 Roundabouts in TRF
Hwy 32 Resurface between TRF and St. Hilaire
Hwy 1 Resurfacing east of TRF
Hwy 1 and 75: Argyle and Warren
Pennington County
Hwy 32 Roundabout at CR 8/Mark Blvd
- This week: The roundabout is open to traffic with the exception of the CR 8 leg which crews have been placing concrete on Marks Blvd connecting to the bridge.
- Next week: Crews will continue work on the CR 8 leg of the roundabout.
- Traffic Impacts: The roundabout is open to traffic except for the east leg of CR 8.
- Website: www.mndot.gov/d2/projects/2020/hwy32-roundabout
CR 8/Mark Blvd route extension and roundabout
- This week: The Challenger Elementary roundabout is open to traffic. At the CR 8 bridge, crews have been working on the approaches and connectors.
- Next week: At CR 8 bridge, crews will work on installation of curb and gutter into the bridge.
- Traffic Impacts: Crews continue working on the connection to the bridge and the CR 8 connection. Crews have continued to haul aggregate base on the east side of the bridge. No traffic impacts.
- Website: www.mndot.gov/d2/projects/2020/airport-road-roundabout
Red Lake Watershed
Westside flood damage reduction Projects
www.mndot.gov/d2/projects/2020/westside-drainage-project
- Construct a diversion channel and drainage infrastructure on the west side of TRF. Underground storm sewer will be installed along Barzen Ave and Greenwood St, along with a new sanitary sewer
-
Storm Sewer & Force Main Installation:
Crews will be completing the 20 inch force main at Greenwood. They will be working on intstallation of storm sewer at Greenwood for the next few weeks.
There is a lane closure on Greenwood Street east of Highway 32 to allow storm sewer installation. This work will take approximately three weeks to complete.
Diversion Channel Construction:
Crews have been placing topsoil along the diversion channel. It is operating with water flowing through.
- Website: www.mndot.gov/d2/projects/2020/westside-drainage-project
- Replace Hwy 1 culvert west of the intersection with Hwy 59
- This week: This work is complete.
- Traffic Impacts: None.
- Replace Pennington CR 7 box culvert
- This week: This is now open to local traffic, use caution. Crews will be paving this portion at the same time as paving operations for County Road 8. Truck traffic is detoured.
- Traffic Impacts: Truck traffic use detour.
Next meeting is on October 6 at 10 a.m., register now:
-
Register prior to the meeting and a confirmation email message will be sent with instructions on how to join the meeting. You can also register just prior to joining the meeting.
To join via phone for audio only
- Dial 1-855-282-6330 or 415-655-0003
- When prompted, use Access Code: 146 294 4235
Project questions? Prior to the meeting, attendees can submit questions through the Comment form on the project website. In the online meeting, attendees are able to submit questions through a Chat feature.
Visit: www.mndot.gov/d2/projects/2020/thief-river-falls
|