ROADSHOW Week of Aug. 24, 2025
Here, you'll find all of the NEW projects, maintenance, and other work taking place in our 11 county district:
Boone, Bracken, Campbell, Carroll, Gallatin, Grant, Harrison, Kenton, Owen, Pendleton, and Robertson Counties
Click the button below to take a look at all of the projects happening right now.
New items or changes in project status are italicized.
*Inclement weather or other unforeseen circumstances may occur, so the information below is strictly of an advisory nature and is subject to change with no notice.
Pothole patching, sweeping, drain & ditch work, litter pick up, brush clearing, culvert repairs and additional work by our KYTC maintenance crews may occur on major interstates/state routes during non-peak daytime hours and at night.
Motorists should watch for roadside maintenance on interstates/highways throughout the district DAILY. We will send out information to the public if these tasks require significant impacts to traffic.
|
|
I-275 CARROLL CROPPER BRIDGE UPDATES
Crews are actively working on three additional expansion joint repairs that were added to the repair project. Preparations for floor beam repairs are also moving forward — phasing and design have been approved, and the final step is getting a scaffolding plan approved before work can begin. More updates on the floor beam repairs will follow.
***
Westbound Traffic (drivers heading from Kentucky to Indiana):
-
On Wednesday, Aug. 20, westbound traffic was switched to the right lane beginning near the Petersburg exit to past the truss of the bridge. Traffic will then shift to the left lane after the truss. This traffic shift is in place to allow contractors space to perform expansion joint repairs.
We've launched a project website via our Driving NKY Progress site to provide the most up-to-date information about the repair project. The website explains the work that is being performed, the work that was added to the original T-1 steel repair project, traffic impacts and includes a frequently asked questions portion that provides valuable information. We will continue to update this site as progress continues.
KENTON AND CAMPBELL COUNTIES
A preventive maintenance project began on Tuesday, June 24, on multiple routes in Kenton and Campbell counties.
The project includes crack sealing, electrical work and application of a thin asphalt overlay known as a thinlay. Thinlays are used as a pavement preservation treatment to restore surface conditions and extend the service life of roads that are still structurally sound.
Crack sealing operations and some electrical work items are complete. Pavement work is currently in progress.
Locations:
Madison Pike (KY 17), Kenton County — From Moffett Road (KY 2042) at mile point 7.97 to just north of KY 14 at mile point 4.94. Paving work is now complete. Rumble strips are the last task for this portion and have not been scheduled.
Dixie Highway (U.S. 25), Kenton County — From Hallam Avenue at mile point 6.26 to Carran Drive at mile point 7.88. Paving work is scheduled to continue Friday night, Aug. 22 and Sunday night, Aug. 24. A single lane closure will be in place from 8 p.m. to 6 a.m. One lane in each direction will be maintained at all times. Weather permitting, this portion of the work is expected to be completed by Monday, Aug. 25.
Alexandria Pike (U.S. 27), Campbell County — From Bluegrass Avenue at mile point 20.49 to Moock Road (KY 1632) at mile point 19.84. Crews will continue pavement prep work on Friday night, Aug. 22. Paving work is scheduled to occur Monday night, Aug. 25, through Wednesday night, Aug. 27. A single lane closure will be in place from 8 p.m. to 6 a.m. One lane in each direction will be maintained at all times. Weather permitting, this portion of the work is expected to be completed by Thursday, Aug. 28.
|
|

-
I-71 – 69.8 – 77.4 mile points – A resurfacing project on I-71 from the Boone/Gallatin County line to the I-71 and I-75 interchange is in progress.
Beginning on Sunday night, Aug. 24, crews will be paving the entrance and exit ramps at I-71, Exit 72 to Verona Mudlick Road (KY 14). Ramps will remain open but narrowed to partial width during working hours.
Work is scheduled during evening/overnight hours of 7 p.m. to 7 a.m., weather permitting:
Sunday, Aug. 24, and Monday, Aug. 25:
-I-71 northbound offramp to Verona Mudlick Road
-Verona Mudlick Road onramp to I-71 northbound
Tuesday, Aug. 26, and Wednesday, Aug. 27:
-I-71 southbound offramp to Verona Mudlick Road
-Verona Mudlick Road onramp to I-71 southbound
Additionally, bridge pier work is nearing completion. Starting Wednesday, Aug. 27, various lane closures will be in place as crews remove barrier walls used during bridge pier work. These closures will continue until all barrier wall is cleared.
Looking ahead – another weekend blitz to begin resurfacing work throughout the project limits is scheduled for after the Labor Day holiday. KYTC will issue an additional update once the schedule is confirmed.
-
North Bend Road (KY 237) – 6.49 – 9.21 mile points – A preventive maintenance project on North Bend Road beginning at Golf Club Drive extending north to just south of Petersburg Road (KY 20) will begin on Friday night, Aug. 22.
Contractors will be applying a thin asphalt overlay known as a thinlay. Thinlays are used as a cost-effective pavement preservation treatment to restore surface conditions and extend the service life of roads that are still structurally sound.
A single lane closure will be in place during the evening/overnight hours of 7 p.m. to 6 a.m. All lanes will reopen by 6 a.m.
Tentative schedule, weather permitting:
Friday, Aug. 22: removing existing thermoplastic striping throughout the project limits.
Sunday, Aug. 24: removing existing intersection markings throughout the project limits.
Tuesday, Aug. 26 – Friday, Aug. 29: begin applying thinlay treatment to the roadway surface. Temporary pavement markings will be applied to the pavement following the end of each shift.
Some work items may also occur during non-peak daytime hours of 9 a.m. to 3 p.m. These tasks will be limited to items that don’t require a lane closure and cause little disruption to traffic.
The project is expected to be completed by Sept. 30, 2025.
-
North Bend Road (KY 237) – 9.21 – 10 mile point – A resurfacing project on North Bend Road from just south of Petersburg Road (KY 20) extending just north of Coral Drive is in progress.
Base failure repairs are now complete. Milling and paving operations is scheduled to begin after Labor Day. To limit traffic disruptions, this portion of the project will take place during the evening/overnight hours of 7 p.m. to 6 a.m.
- Petersburg Road (KY 20) – 13.8 – 14.6 mile points – A gas main installation project on a portion of Petersburg Road is now complete.
- Mineola Pike (KY 3076) 0.0 – 0.9 mile points – All corrective work items on the widening and improvement project on Mineola Pike is now complete.
|
|

-
AA Highway (KY 9) – 0.0 – 5.39 mile point – A resurfacing project on a portion of the AA Highway beginning at the Mason/Bracken County line extending north to just south of KY 19 began on Thursday, Aug. 21.
A single lane closure will be in place during working hours of 7 a.m. to 7 p.m. with flaggers on-site to direct traffic around the work zone.
Motorists are advised to plan ahead and expect delays during working hours. Weather permitting, the project is expected to be completed by Nov. 15, 2025.
|
|

-
U.S. 42 – 0.17 – 3.33 mile point – A resurfacing project on U.S. 42 beginning near Nucor Steel extending east to the north ramps of KY 1039 is in progress.
Base failure repairs and milling/paving operations are now complete. Thermoplastic striping and rumble strip work still remains.
|
|

-
KY 22 – 10.68 – 11.55 mile point – A diamond grinding and roadway improvement project on KY 22 between Warsaw Road (KY 467) and U.S. 25 is scheduled to begin on Sunday, Aug. 24.
Work will be completed in phases and include diamond grinding and grooving of pavement, partial depth pavement repairs, sidewalk and curb work, guardrail replacement, and installation of permanent striping and pavement markers. A new radar detection system will also be added at signalized intersections within the project limits, replacing embedded traffic loops.
Beginning on Sunday, Aug. 24, crews will start with partial depth pavement repairs. This work will require single lane closures during overnight working hours of 8 p.m. to 7 a.m.
After Labor Day, crews will return to begin diamond grinding and other remaining improvements. Overnight lane closures will continue from 8 p.m. to 7 a.m., with one lane in each direction maintained at all times. Flaggers will be present when work is occurring in intersections.
Some work items may also occur during non-peak daytime hours. To minimize traffic impacts, any daytime closures will be limited to the western portion of the project. All work requiring lane closures on the eastern portion will take place overnight.
No lane closures will be in place during the Labor Day or Thanksgiving holiday weekends.
Weather permitting, the project is expected to be completed by Nov. 30, 2025.
-
I-75 – 157.7 – 162.7 mile points – A resurfacing project on a five-mile stretch of I-75, from just south of Dry Ridge to just north of the Sherman Mt Zion Road (KY 1994) overpass is in progress.
All lane closures on I-75 have reopened following the completion of milling/paving operations. The contractor is working on final tasks within the project limits including final thermoplastic striping, pavement marker and rumble strip installation.
|
|

-
Interstate 275 Westbound Ramp to I-71/75 Northbound – 0.0 – 0.6 mile points – A drainage improvement project is now complete.
-
Interstates 71/75 – 183.83 – 190.5 mile points – A drain clearing project will begin on Monday, Aug. 25. Crews will perform drain clearing operations from the Cut in the Hill to Donaldson Highway. This work will take place between the hours of 8 p.m. and 5 a.m. and will require a single left lane closure. All lanes will reopen by 5 a.m. Crews will begin working southbound. Once southbound drains have been cleared, the maintenance crew will shift to northbound operations. This work is expected to be completed Friday, Aug. 29 at 5 a.m.
-
Interstates 71/75 Texas Turnaround Ramp – beginning Monday, Aug. 25 through Thursday, Aug. 28, crews will be performing soil boring work that will require the Texas Turnaround ramp to be closed between the hours of 8 a.m. and 4 p.m. The ramp will reopen daily by 4 p.m. Motorists can detour using I-71/75 southbound to Pike Street exit, turn left on Pike Street, and then left onto I-71/75 northbound. Weather permitting, this soil boring work is expected to be completed Thursday, Aug. 28 at 4 p.m.
-
Interstates 71/75 Northbound – 188.3 – 190.5 mile points – Soil boring work will take place on Monday, Aug. 25 and Tuesday, Aug. 26 requiring a single right lane closure from south of Kyles Lane (KY 1072) to north of Martin Luther King Jr. Blvd. This lane closure will be in place from 9 p.m. to 6 a.m. The lane will reopen by 6 a.m. This soil boring work is expected to be completed Wednesday, Aug. 27 at 6 a.m.
-
W. Fourth Street (KY 8) On-Ramp to I-71/75 Southbound – From Tuesday, Aug. 26 through Friday, Aug. 29, there will be an on-ramp closure from W. Fourth Street to I-71/75 southbound between the hours of 9 p.m. and 6 a.m. The ramp will reopen daily by 6 a.m. Motorists can detour using E. Fifth Street to Main Street (U.S. 25), to Pike Street, to I-71/75 southbound. This boring work is expected to be completed Saturday, Aug. 30 at 6 a.m.
-
Bristow Road (KY 1303) – 0.0 – 0.92 mile point – A widening and safety improvement project on Bristow Road from the KY 536/KY 1303 intersection to the Beechgrove Elementary School is in progress.
A traffic shift took place on Wednesday, Aug. 20. This shift moved motorists to the new pavement from south of Beechgrove Drive (0.75 mile point) to north of Timber Lane (0.55 mile point).
-
Whites Road (KY 1930) – 0.0 – 1.19 mile points – Beginning Monday, Aug. 25, KYTC maintenance crews will be performing culvert repairs along a stretch of Whites Road. Work will take place daily between 8 a.m. and 4 p.m. The road will be blocked to thru traffic during these hours. The road will reopen daily by 4 p.m. Weather permitting, this maintenance project is expected to be completed Friday, Aug. 29 at 4 p.m.
-
Dixie Highway (U.S. 25) – 5.04 – 5.23 mile points – A KYTC Boone County maintenance project is in progress.
The lane closure has been temporarily removed, and a steel plate is covering the work area. Crews will return Wednesday night, Aug. 27, to continue repair work at this location. A single lane right lane closure will be in place beginning at 10 p.m. and is expected to remain in place until the work is complete.
This project is expected to be completed by Friday, Aug. 29.
|
|
Didn't see the project you're looking for?
This report highlights NEW projects and UPDATES for on-going projects. Our website roadshow stores ALL the information for all the projects that are currently taking place around the district. Please visit the link below for the most detailed project descriptions.