ROADSHOW Week of June 15, 2025
Here, you'll find all of the NEW projects, maintenance, and other work taking place in our 11 county district:
Boone, Bracken, Campbell, Carroll, Gallatin, Grant, Harrison, Kenton, Owen, Pendleton, and Robertson Counties
Click the button below to take a look at all of the projects happening right now.
New items or changes in project status are italicized.
*Inclement weather or other unforeseen circumstances may occur, so the information below is strictly of an advisory nature and is subject to change with no notice.
Pothole patching, sweeping, drain & ditch work, litter pick up, brush clearing, culvert repairs and additional work by our KYTC maintenance crews may occur on major interstates/state routes during non-peak daytime hours and at night.
Motorists should watch for roadside maintenance on interstates/highways throughout the district DAILY. We will send out information to the public if these tasks require significant impacts to traffic.
|
|
IMPORTANT REMINDERS!
The 10-Day Closure of the Clay Wade Bailey Bridge HAS BEEN POSTPONED!
Due to additional repairs and inclement weather, the ten-day closure to install three modular joints on the bridge has been postponed and extended. Beginning at 5 a.m. on Wednesday, June 18, the bridge will be closed to all vehicular traffic, but pedestrians and bicyclists will still have access.
A signed detour will be in place during the closure utilizing the Brent Spence Bridge and Taylor Southgate Bridge. Motorists should expect delays and heavier traffic on surrounding bridges. Plan ahead, leave early and consider alternate routes.
The closure will now be in place for 13-days, and the bridge is expected to reopen by 5 a.m. on Monday, June 30.
Closure of Bristow Road (KY 1303) at KY 536 in Kenton County
Beginning Sunday, June 15, a 45-day closure will be in place on Bristow Road from south of Timber Lane to the intersection of KY 536 and KY 1303. This will allow a safe area for crews to begin constructing a roundabout at the intersection. Through traffic on KY 536 will be maintained. Local traffic will be maintained on KY 1303 from Richardson Road to Timber Lane.
Motorists can detour using KY 536 to Dixie Highway to Industrial Road.
NOTE: the bridge east of Dixie Highway on Richardson Road currently has a weight limit of three tons. Any vehicles weighing more than three tons should use Industrial Road as a detour.
The closure is expected to be in place through Aug. 1, 2025. Learn more about this project here.
|
|

-
Big Bone Road (KY 1925) – 0.0 – 3.18 mile point – A resurfacing project on Big Bone Road from KY 338 to Rice Pike is now complete. Some corrective striping work is scheduled to take place within the next couple of weeks.
-
Donaldson Highway (KY 236) 0.0 – 1.6 mile points – A widening and safety improvement project on KY 236 (Donaldson Highway) between KY 842 (Houston Road) and KY 3076 (Mineola Pike) is in progress.
The entrance to South Airfield Drive from Donaldson Highway will temporarily close beginning at Noon on Sunday, June 22.
The closure was scheduled in partnership with Cincinnati/Northern Kentucky International Airport (CVG) to support work planned for the South Airfield Tunnel. While CVG crews complete their work, KYTC will take advantage of the closure to perform cement stabilization at the South Airfield Drive intersection as part of the Donaldson Highway widening project.
Additionally, Cherry Tree Lane and Queensway Drive will also close for stabilization work.
South Airfield Drive, Cherry Tree Lane and Queensway Drive are expected to reopen by 8 p.m. on Monday, June 30.
KYTC has coordinated closely with CVG to help minimize traffic impacts. Messages boards will be in place to provide advance notice of the upcoming closures.
|
|

-
E. Main Street (KY 10) – 3.4 – 3.65 mile points – A slide repair project on E. Main Street will begin on Monday, June 9. Crews will repair a slide near Redstone Road. The road was damaged due to flooding in April. This work will require a full road closure between the hours of 7 a.m. and 5 p.m. The road will reopen daily at 5 p.m. with a single lane closure. Motorists will use a temporary signal to get through the work zone. Weather permitting, the project is expected to be completed Friday, June 27. **This project has been extended**
-
High Friction Surface – Various Routes – Several traffic impacts will be in place during evening/overnight hours for the application of high friction surface treatment on various routes in Campbell County.
High friction surface application is now completed. Thermoplastic striping is the last step of this project and work will occur at/near the areas listed in our full roadshow report. Please watch for crews performing this work.
|
|

-
U.S. 127 – 3.45 – 5.95 mile points – A slide repair project on four different locations on U.S. 127 is now complete.
|
|

-
KY 491 – 0.02 mile point – A bridge replacement project on the KY 491 crossing over Bullock Pen Creek between Rainbow Drive and KY 1942 is scheduled to begin Monday, June 23.
To accommodate the work, the bridge will be closed to traffic during construction beginning Monday, June 23. A signed detour will be in place to guide motorists around the closure.
The bridge is expected to reopen to traffic on Monday, Aug. 11. Additional work will continue throughout the project area following the reopening until all project tasks are complete.
The project is expected to be completed by Aug. 30, 2025.
-
Keefer Road (KY 2936) – 0.0 – 3.69 mile point – A resurfacing project on Keefer Road from Keefer Lawrenceville Road to U.S. 25 is in progress.
Base failure repairs are now complete. Weather permitting, milling/paving operations are expected to begin the week of June 23.
-
Gardnersville Road (KY 491) – 3.98 – 5.42 mile point – A resurfacing project on Gardnersville Road from U.S. 25 to North Folk Drive is in progress.
Base failure repairs are now complete. Weather permitting, milling/paving operations are expected to begin the week of June 23.
|
|

- Richardson Road (KY 1829) – 2.72 – 3.98 mile points – A slide repair project is nearing completion. Richardson Road will reopen to traffic on Friday, June 13 during the afternoon hours. Crews have completed the slide repair, drainage/ditching operations, and have laid a base layer of pavement in areas where work was performed. Crews will return to this area at a later date to complete the milling/paving operations in the project area.
|
|
Didn't see the project you're looking for?
This report highlights NEW projects and UPDATES for on-going projects. Our website roadshow stores ALL the information for all the projects that are currently taking place around the district. Please visit the link below for the most detailed project descriptions.