New Smithland Bridge Truss Lift and Placement Halted Until Wednesday Morning
Work to resume at 7:30 a.m., Wednesday
PADUCAH, Ky. (Sept. 13, 2022) – The lift and placement of the truss for the new Smithland Bridge halted for the evening about 6:20 p.m.
After a power unit for one of the lifting towers failed, engineers came up with a work-around to allow the lift to continue. However, when a second power unit had to be taken out of service the lift had to be halted.
Replacement power units are en route and expected to arrive at the construction site early Wednesday.
The effort to lift the 700 ft - 5.1 million pound steel truss into place is expected resume at 7:30 a.m., Wednesday.
Revised Wednesday Schedule
7:30 a.m. - Resume lift 10 a.m to 11 a.m. - Slide truss into place over the main piers 11 a.m to Noon - Lower truss into position on main piers 1 p.m. - Start disassembly of jacking towers to allow flotilla to leave the bridge
Photos and video of work at the site today are available at www.facebook.com/kytcdistrict1.
Updates at appropriate.
A lane restriction on the existing U.S. 60 Cumberland River Bridge at Smithland will remain in place until the truss is placed on the new bridge. Motorists should be prepared for one lane traffic with alternating flow controlled by an automated signal. Delays are likely during peak travel periods.
To get traffic advisories and alerts for KYTC District 1 counties via email please go to https://public.govdelivery.com/accounts/KYTC/signup/13651. Click on the District 1 counties you regularly drive through, or on any of the specialty corridors you travel. Check your SPAM filtering to assure Gov Delivery is on your approved list.
Timely traffic advisories for the 12 counties of KYTC Highway District 1 are available by going to www.facebook.com/kytcdistrict1. You do not have to be a Facebook member to access this page.
Navigate traffic at goky.ky.gov, at waze.com, or with the WAZE App.
###
|