Resurfacing operations scheduled for Scott County
Cynthiana Road/US 62 and Georgetown Road/US 460
LEXINGTON, Ky. (April 9, 2021) – The Kentucky Transportation Cabinet (KYTC) advises motorists of a resurfacing project scheduled for Cynthiana Road/US 62 and Georgetown Road/US 460. The work will include; asphalt repairs, milling/paving and sidewalk ramp improvements.
The project was awarded to Nally & Gibson Georgetown LLC DBA in the amount of $2,003,564.43. The anticipated completion date for the entire contract (both US 62 and US 460) is Wednesday, June 30.
Cynthiana Road/US 62
Monday, April 12 – work will begin with the hours of 7 p.m. until 6 a.m. evenings/mornings (Mon. – Fri.)
- work will be in effect between milepoints 13.310 and 18.940
- this location begins at KY 3487 and extends East to the Scott-Bourbon County line (a distance of 05.63 miles)
- at least one lane will remain open at all times for motorists
- flaggers will be onsite at specific periods to guide and direct the traveling public
Georgetown Road/US 460
Monday, April 12 – work will begin with the hours of 7 a.m. until 3 p.m. weekdays (Mon. – Fri.)
- work will be in effect between milepoints 8.583 and 11.497
- this location begins at the pavement joint for Paynes Depot Road and extends East to the pavement joint approximately 1108 feet East of Scotland Drive (a distance of 02.91 miles)
- at least one lane will remain open at all times for motorists
- flaggers will be onsite at specific periods to guide and direct the traveling public
All work, and closures are scheduled on a tentative basis, and subject to change depending on weather, emergencies, and other factors beyond the control of the Department of Highways.
District 7 includes: Anderson, Bourbon, Boyle, Clark, Fayette, Garrard, Jessamine, Madison, Mercer, Montgomery, Scott, and Woodford Counties