Billtown Road Improvements to Begin Next Week and last until Until Spring of 2025

Billtown Road Improvements to Begin Next Week and last until Until Spring of 2025

The following improvements will be constructed throughout the upcoming year:

 

  • Easum (turning lanes)
  • Lovers (turning lanes)
  • Mary Dell (with school flasher)
  • Michael Edward (turning lanes)
  • Fairground (with signal installation)
  • Vantage Creek (turning lanes)
  • Colonnades (turning lanes)

Flynn Construction is scheduling to have crews on the project stated above the week of 4/15/2024.  The week prior to starting (4/8/2024), Flynn will be onsite to start doing layout/staking for the waterline and casing but will not be in the roadway.  Some layout has been completed to date. 

 The following preparations will begin 4/8/2024

  • Place Variable Message Boards
  • Layout and Staking – 4/8 (Crew will not be in the roadway or hindering traffic)
  • Mobilization – 4/15
  • Receive Materials – 4/15 and throughout the week
  • Install Casings (Phases 1-3)
  • Waterline – 12” Phase 3 (This will commence following the installation of all the casings)
  • Storm – Phase 3 (This will commence the same time as the waterline of phase 3, with a second crew)
  • Clearing – TBD, as needed