Road Closed to Replace a Culvert on South Watterson Trail North of Ferndale Avenue

a

Starting September 4, 2023, Basham Construction is planning to begin work to replace a culvert on S Watterson Trial just north of Ferndale Ave.   Associated with this work will be roadway improvements north of the culvert to secure the retaining walls which exist currently and repaving of the roadway within those limits.  Construction is anticipated to last until November 22, 2023.  Below is the planned detour which will  be in place through the duration of the project.  .