Chicago Street Corridor Progress Update

Chicago Street Corridor Progress Update

Post Date: 08/11/2025 11:45 AM

Work that has been addressed the week of August 4th:

  • Construction fencing has been removed along the sidewalks in all areas except in front of the library
  • All four shade structures in the square are now complete
  • Electrical primary ducts have been installed to Ottawa Street

Work that will be addressed the week of August 11th:

  • Masons will continue with stone placement work in the city square
  • Electrical work to install light foundations and controllers will continue in the square
  • Electricians will continue with installation of city fiber optic conduits along Washington Street.  Parking in this area will remain restricted.
  • Work at the entrance to the Ottawa Street Parking Garage can be expected. Concrete placements will require a closure, and advance notice of that closure will be provided once the timing is established

Sidewalk fencing has now been removed in areas where streetscape improvements are nearing completion 

Sidewalk fencing has now been removed in areas where streetscape improvements are nearing completion

The shade structures can now be viewed in their final form 

The shade structures can now be viewed in their final form

Overview of the north side of the square, with masonry work on the gathering area beginning 

Overview of the north side of the square, with masonry work on the gathering area beginning