Chicago Street Corridor Progress Update
Joliet, IL sent this bulletin at 08/11/2025 11:46 AM CDTChicago Street Corridor Progress Update
Post Date:
08/11/2025 11:45 AM
Work that has been addressed the week of August 4th:
- Construction fencing has been removed along the sidewalks in all areas except in front of the library
- All four shade structures in the square are now complete
- Electrical primary ducts have been installed to Ottawa Street
Work that will be addressed the week of August 11th:
- Masons will continue with stone placement work in the city square
- Electrical work to install light foundations and controllers will continue in the square
- Electricians will continue with installation of city fiber optic conduits along Washington Street. Parking in this area will remain restricted.
- Work at the entrance to the Ottawa Street Parking Garage can be expected. Concrete placements will require a closure, and advance notice of that closure will be provided once the timing is established
|
Sidewalk fencing has now been removed in areas where streetscape improvements are nearing completion |
|
The shade structures can now be viewed in their final form |
|
Overview of the north side of the square, with masonry work on the gathering area beginning |
|