DDOT's Weekly Construction Update: Work Between Sunday, July 15 and Saturday, July 28
District of Columbia sent this bulletin at 07/13/2018 04:36 PM EDT
Work Between Sunday, July 15 and Saturday, July 28
Friday, July 13, 2018
DC Is Your Sports Capital! For up-to-date information about
construction, closures, city services, and getting around during upcoming
festivities, please visit: sportscapital.dc.gov
Mayor Bowser is committed to eliminating all roadways, alleys, and sidewalks in poor condition in Washington, DC by 2024 through the PaveDC initiative. This publication lists all of the road, alley, and sidewalk paving projects that will be under construction during the next two weeks. For more information about these projects, please visit DDOT's interactive tool, PaveDC.
Please note: Work may be adjusted depending on weather and other conditions. Additional projects may be added to this list. DDOT contacts residents and businesses within the work zones before work begins. Unless otherwise noted, work is not conducted on weekends.
As part of DDOT's commitment to improving and restoring local roadways, activities will be conducted at the following locations throughout the following two weeks, weather permitting:
Ward 1
Intersection of U Street NW, between 14th Street NW and
17th Street NW
Ward 2
D Street NW, between 17th Street NW and 18th Street NW
Decatur Place NW, between Massachusetts Avenue NW and
Florida Avenue NW
Cambridge Place NW, between 30th Street NW and Avon
Place NW
26th Street NW, between Pennsylvania Avenue NW and M
Street NW
Ward 3
Davenport Street NW, between Nebraska Avenue NW and
36th Street NW
Edmunds Street NW, between 39th Street NW and 41st
Street NW
Van Ness Street NW, between Connecticut Avenue NW and
Dead End
Ward 4
Madison Street NW, between Kansas Avenue NW and 1st
Street NE
Ward 5
19th Street NE, between Benning Road NE and H Street NE
19th Street NE, between Maryland Avenue NE and I Street
NE
Kearny Street NE, between 17th Street and 18th Street
NE
Otis Street NE, between 10th Street NE and 12th Street
NE
Faraday Place NE, between 6th Place NE and South Dakota
Avenue NE
Perry Place NE, between 10th Street NE and Dead End
South Dakota Avenue NE, between 13th Place NE and Rhode
Island Avenue NE
18th Street NE, between Benning Road NE and I Street NE
31st Place NE, between South Dakota Avenue NE and
Banneker Drive NE
31st Place NE, between Banneker Drive NE and Fort
Lincoln Drive NE
Upshur Street NE, between 12th Place NE and 13th Street
NE
Meigs Place NE, between 16th Street NE and Bladensburg
Road NE
6th Place NE, between Buchannan Street NE and Dead End
Ward 6
Intersection of Independence Avenue SE and 14th Street
SE
M Street SE, between 7th Street and Half Street SE
2nd Street SW, between Q Street SW and R Street SW
5th Street NW, between M Street NW and O Street NW
Constitution Avenue NE, between 20th Street NE and 21st
Street NE
G Street NE, between 14th Street NE and 15th Street NE
L Street SW, between Delaware Avenue SW and 3rd Street
SW
Ward 7
48th Place NE, between Fitch Place NE and Foote Street
NE
Burns Street SE, between Texas Avenue SE and Gorman
Street SE
55th Street NE, between James Place NE and Eastern
Avenue NE
Erie Street SE, between 29th Street SE and 30th Street
SE
Benning Road NE, between 42nd Street NE and East
Capitol St NE
Quarles Street NE, Anacostia Avenue NE and Kenilworth
Avenue NE
S Street SE, between 29th Street SE and 30th Street SE
Ward 8
Interstate 295, between Malcolm X Avenue SE and
Laboratory Road SE
As part of DDOT's commitment to the improvement and restoration of local sidewalks, construction activities will occur at the following locations throughout the next two weeks.
Ward 4
Oglethorpe Street NE, between Riggs Road NE and 8th
Street NE
Ward 5
Mills
Avenue NE, between Rhode Island Avenue NE and Hamlin Street NE
Ward 6
O Street SW, between South Capitol Street SW and
First Street SW
DDOT will improve alleys at the following locations. Once work begins, access to parts of the alley under construction will be closed, and parking will not be available. In emergency situations, access may be permitted by notifying DDOT. Work is estimated to take about two weeks, weather permitting.
Ward 4
Square 3368,
bound by Van Buren Street NW, Sandy Spring Road NW, and Underwood Place NW
Square 2736, bound
byFloral Street NW, 15th Place NW, Alaska Avenue NW and 14th
Street NW
Square 3405, bound
by New Hampshire Avenue NW, Missouri Avenue NW, 1st Street NW and Ingraham
Street NW
Square 3211,
bound by Hamilton Street NW, 5th Street NW, Gallatin Street NW and 7th
Street NW
Ward 5
Square
4209, bound
by Rhode Island Avenue NE, 20th Street NE, and Hamlin Street NE
Ward 7
Square 5150, bound by 48th Street NE, Hunt Place NE, 46th
Street NE and Hayes Street NE
If you live near any of the project areas, please remove your vehicles by the posted times, and encourage your neighbors to do the same.