 October/November 2026
|
|
|
The CAL-ACCESS Replacement System (CARS) Project team conducted an assessment to determine the readiness of the new CAL-ACCESS system to go-live on November 16, 2026. Following the readiness assessment, it was determined that the most viable go-live date for the new CAL-ACCESS system is February 16, 2027.
Significant progress has been made on the project, with three of the four program increments robustly tested and accepted. Resulting from this testing effort, additional needed functionality was identified that is associated with filing the Form 460 Recipient Committee Campaign Statement, the public’s ability to perform bulk download, and changes related to recently adopted legislation. The project team determined a 90-day delay to the planned go-live date will allow the development team additional time to develop and test this additional functionality and deliver a high-quality system that meets the requirements for the new CAL-ACCESS system. Full support for this short delay has been received from the fourteen third-party software vendors who will certify their systems are ready to submit filings on behalf of their clients to the new CAL-ACCESS system, from the partner agencies and from members of the filing community.
For filers preparing to submit lobbyist entity registration and renewal documents for the upcoming legislative session, and those who will submit disclosure filings in January, they should file the required paperwork in the same manner used in past filings. A notification letter was emailed to lobbying entities on October 29, 2026, and mailed via the United States Postal Service to entities who do not have an email address on file with the Office of the Secretary of State.
A copy of these filing instructions, of upcoming filing dates, planned training dates, and other resources are located on the CARS Go-Live Resources page.
Also in this edition:
- Initial Testing Feedback from External User Testers
- Major Milestones
- Getting Ready for Go-Live
- On the Calendar
- Question of the Month
- Your Voice in the CAL-ACCESS Transition
|
|
|
The external stakeholder testing window began on September 14 and ended on October 16, 2026. More than 80 volunteers accessed the test environment, with users representing the interests of lobbying, campaign, partner agencies, and public data users. Participants were given step-by-step instructions known as test scripts to guide them through an initial round of testing. Once they completed their test scripts, these testers had the opportunity to perform exploratory testing where they were able to navigate freely and use the system as they would in a real-life scenario. All testers were asked to provide feedback and identify any parts of the system that were unclear to them; report system activity that appeared to be a system bug or working incorrectly; and identify the functionality they liked. Items reported as bugs were re-tested by a Political Reform Division subject matter expert, and all confirmed bugs were discussed with the prime vendor. All testers were encouraged to complete an “end of testing” survey and were invited to a “wrap up” meeting held on October 21 during which they were asked to share details of their testing experience and overall perspective of the new CAL-ACCESS.
A summary of the testing results is shown here.
- There were 524 feedback items received during the testing window. These items were related to the filer, partner, and public portals.
- Bugs – 179
- Training needed – 96
- Design suggestions – 77
- Help text suggestions – 64
- Functionality not available to test yet – 38
- Working as expected – 22
- Positive feedback – 48
- This feedback shows that approximately 34% of the total feedback items are bug related, with the remaining 66% related to suggestions for changes to system screens or to help text.
Testing feedback is very helpful to the project team and helps them make changes to instructional text, help screens, and training resources prior to the availability of the new CAL-ACCESS on February 16, 2027.
Another opportunity to participate in external user testing will occur in mid-January 2027. Details explaining the sign-up process will be provided in mid-December 2026.
|
|
|
The project milestones and key achievements reached during the past month include:
- The program Increment IV development effort is nearing completion and undergoing testing before final approval.
- The data conversion team has migrated more than 282 million records to the new CAL-ACCESS system. The data conversion effort will continue until the new system is made available to the public.
- Third-party software vendors continue testing the application program interfaces (APIs), confirming when campaign and lobbying data upload accurately, and reporting issues when needed.
- Simplified output report formats are now available on the CARS Go-Live Resources page. The goal of this new report format is to provide submitted registration and disclosure information in an easy-to-read format. System users are encouraged to review the report formats and provide feedback if missing fields or information are detected.
|
|
|
The CARS Project team encourages completing the following steps before February 16, 2027:
- Keep an eye out for details that describe upcoming training options. Initial training dates will be available by mid-December 2026 and will be available on the CARS Go-Live Resources webpage. Training options will include online training via Microsoft Teams, training videos specific to filing activities such as registering for either lobbying or campaign, creating lobbying and campaign disclosures, short instructional videos such as how to access and log in to the system, written user guide documentation, and frequently asked questions and answers.
- Review the available resource documents and become familiar with the crosswalk that compares the current Fair Political Practices Commission (FPPC) form numbers for lobbying and campaign activity to the report names used in the new CAL-ACCESS system, the simplified output report formats, legislative changes that will become effective with the new CAL-ACCESS, upcoming filing deadline dates, and expenditure code changes effective with the new CAL-ACCESS. All are available on the CARS Go-Live Resource
|
|
- The next third-party software vendor meeting is November 10, 2026, 10:30-11:00 a.m.
- Collaborative training sessions will be scheduled with the FPPC. The specific training times and links to the training classes will be posted on the CARS Go-Live Updates page and on the FPPC training page.
- The next CARS Monthly External Stakeholder meeting is scheduled for November 4, 1:30–2:30 p.m. A meeting invite and update has been sent out. The October and November newsletters are combined in this newsletter edition.
- The new CAL-ACCESS go-live date is February 16, 2027.
|
|
|
What do I need to be ready for the new CAL-ACCESS by February 16, 2027?
As soon as possible, use the current submission process to submit all required paper filings for registration and disclosure. This will allow PRD staff sufficient time to process the filings for inclusion in the final data conversion and migration to the new CAL ACCESS system. When training becomes available, plan to complete training before February 16, 2027. The project team is available to answer questions at PRDCARS@sos.ca.gov and at the monthly External Stakeholder Meetings.
|
|
|
As always, the project team wants you to ask any questions you have about the CARS Project. Questions asked and responses provided will be included in future editions of the newsletter and posted as FAQs on the CARS Go-Live Updates page.
What is your biggest remaining question before go-live?
Please give us your thoughts in the poll link here.
|
|
|
What would you like to see included in the next CARS Stakeholder Bulletin issue? Email PRDCARS@SOS.CA.GOV to provide your ideas and feedback.
|
|
The CARS Project Monthly External Stakeholder Meeting Series (MS Teams), PowerPoint Presentations, Q&As, and FAQs may be found on the CARS Homepage.
|
|
|
|
|