Oakland Int'l Airport Bulletin

 

Oakland International Airport

OAKLAND INTERNATIONAL AIRPORT

AIRPORT BULLETIN 

 

SUBJECT:         Elevators “Out of Service” for work tonight in Terminal 1 and 2

 

DATE:                 March 5, 2012  

                                   

 

Scope of Work:

 

As part of the Terminal 1 Renovation project, Turner Construction, Allied Fire Protection, FDU, Inc, and KONE, Inc. will be performing work in the elevators of Terminal 1 and 2. During the night, each elevator will be placed out of service individually by KONE Elevators. Contractors will be replacing end of line resistor for the fire alarm speakers and installing fire sprinklers in the M103 3-stop elevator. Signage will be posted for the closure of each elevator.

 

Airport Engineering will be onsite to coordinate activities with Landside and Airside Operations and ESEs.

 

 

Construction Duration and Planned Schedule:

 

Date(s):                        Monday, March 5th, 2012 to Tuesday, March 6th, 2012

Work Day(s):                One (1)

Work hours:                  2100 to 0400 hours

 

Vehicles:

 

Construction vehicles will display the appropriate placards. Vehicles will be parked in Turner’s Construction lay down area between Gates 8 and 8A.

 

Vehicles will at all times comply with Oakland International Airport, Airport Operations Area (AOA) Vehicle Safety Rules 406.2.

 

Personnel Identification:

 

Turner Construction, Allied Fire Protection, Inc., FDU, Inc. and KONE Elevators contractors are properly badged for the work area or will be under escort of badged personnel.

 

 

 

           

Special Instructions and/or restrictions:

 

Work site will be kept clean and free of debris after completion of work.

           Testing of the elevators will commence after the completion of work.

 

 

 

Contact Information:

 

Port Staff: Engineering and Facilities

Alvin Kan (AP114)

Contact: 510-466-7807

Mobile: 510-715-8741

 

Contractor: Turner Construction

Site Superintendent:

Brian Muldoon 

Mobile:  510-812-2215  

 

Project Manager:

Brendan Greeen

Mobile: 415-286-1826

 

            Contractor: FDU, Inc.

Supervisor: Chris Collum

Mobile:      707-628-3211

 

Contractor: Allied Fire Protection

Site Superintendent:

Brian Archer    

Mobile:  510-759-1829

 

Contractor: KONE Elevators:

Site Superintendent:

Scotty Broom

Mobile: 707-974-8176

 

Distribution:

 

Director of Aviation

 

Assistant Director of Aviation

Airport Business Manager

Airport Operations Manager, Airside

ABC Security Project Manager

Airport Operations Manager, Landside

Airport Operations Supervisor

Aviation Security Manager

     Operations Reading File

Superintendent, Airside

     Operations Coordinator

Superintendents, Landside

     Operations Dispatcher

Superintendent, Security

     Communications (Switchboard)

Superintendent, Business

Airport Facilities Maint. Manager

Airport Properties

Equipment Systems Superintendent

Airport Technical Comm. Supervisor

Airport Utilities

Noise Abatement/Environ.

Airport Maintenance/Garage

Keiser & Associates (Cargo Cnslt)

Airport Construction

Aviation Marketing & Communications

Airport Tenants

Alameda County Sheriff, Aviation Unit

Rental Car Shuttle

 

 

 

 

You are subscribed to Airport Bulletin for Port of Oakland, California. This information has recently been updated, and is now available.