OAK Bulletin - SecurityPoint Media's SPM Connex - T2 Pass. Sec. Ckpt.

 

Oakland International Airport

OAKLAND INTERNATIONAL AIRPORT
AIRPORT BULLETIN 

 

 

SUBJECT:

 

SECURITYPOINT MEDIA'S "SPM CONNEX"

 

 

PROJECTOR MAINTENANCE

 

 

TERMINAL 2 PASSENGER SECURITY CHECKPOINT

 

 

 

DATE:

 

JUNE 13, 2016

 

 

 

 

 

 

 

 

 

 

Location and Scope of Work: 

As part of SecurityPoint Media's "SPM Connex" AKA Terminal 2 Passenger Security Checkpoint Enhancement, Columbia Electric will perform maintenance on three (3) commercial projectors.  

 

Project Duration and Planned Schedule: 

Work Day(s): 

Two (2)

Dates & Hours:

11:00 PM 06/13/16  to  3:00 AM 06/14/16  

 

 

Vehicles:

 

 

 

 

Terminal 2 Lot:  Contractor vehicle parking   

 

 

 

 

 

Personnel Identification:

Contractor work crew will possess valid identification. 

Crew Leader possesses OAK I.D. badge.

 

 

 

 

 

Special Instructions and/or Restrictions:

During the Planned Schedule, the work site is designated as a pre-security location. No hot work will be performed.  Work site will be clean and free of debris after completion of work.  A hydraulic lift will not be used. 

 

 

 

Contact Information:  

  

 

Oakland International Airport

Contact:

 

Doug Johnson, Airport Properties (off-airport)

  Mobile:

 

(510) 719-6912

Contact:

 

Manager on Duty ("MOD"), Airport Operations (on-airport 24/7)

  Office:

 

(510) 563-3361

 

 

 

Contractor:

 

Columbia Electric

Contact:

 

Nick Scruggs, Project Manager (on-site for lift delivery/retrieval only)

  Mobile:

 

(925) 719-2959

 Contact:

 

Dan Kimmel, Crew Leader - Electrician (on-site); OAK badged 

Mobile: 

 

(415) 271-9048 

     

       Tenant:

 

SecurityPoint Media

Contact:

 

Amy Engster, Manager (off-site)

Mobile:

 

(518) 322-7552


 You are subscribed to Airport Bulletin for Port of Oakland, California. This information has recently been updated, and is now available.