Caltrans Construction Update for State Route 49/ Gold Country Corridor

CALTRANS CONSTRUCTION UPDATE

Route 49 Construction Update for Gold Country Corridor


Caltrans is reminding motorists of various lane closures in multiple locations along State Route 49 as several projects continue work in Placer County.

Here is the breakdown for this week:

Safety Barrier Project

  • Northbound and southbound between Lorenson Road/Florence Lane and Lone Star Road, various lane closures are scheduled from 7 a.m. to 4 p.m. Monday, May 5 through Friday, May 9.
  • Northbound and southbound between Lorenson Road/Florence Lane and Lone Star Road, various lane closures are scheduled from 7 p.m. to 7 a.m. Monday, May 5 through Friday, May 9. Work is scheduled to end for the week at 7 a.m. Saturday, May 10.

Sidewalk Gap Closer Project

  • Northbound between Elm Avenue and Palm Ave, various lane closures are scheduled from 7 p.m. to 7 a.m. Monday, May 5 through Thursday, May 8. Work is scheduled to end for the week by 7 a.m. Friday, May 9.

Secondary Sidewalk Project

Northbound between Edgewood and Holly Vista Way, various lane closures are scheduled from 4 a.m. to 10 a.m. Tuesday, May 6 through Thursday, May 8.

The extended lane closures will help to minimize the duration of the work and improve workers’ safety. Motorists may experience delays between 10 and 15 minutes, depending on traffic volumes. The schedule is subject to change or be delayed due to weather, availability of materials or other unexpected events. 

Caltrans District 3 is responsible for maintaining and operating 4,385 lane miles in 11 Sacramento Valley and Northern Sierra counties. Caltrans reminds motorists to “Be Work Zone Alert” and slow in construction zones for the safety of travelers and crews performing these improvements. Please reach out if you have any questions. 

For real-time traffic information, click on Caltrans’ QuickMap 

Caltrans issues construction and road condition updates on X @CaltransDist3 and on Facebook at CaltransDistrict3