Roadway Improvements & Traffic Advisories for February 12–19, 2025

Roadway-Improvement-&-Traffic Advisory-Header_3

Road Construction & Improvement Projects

February 12–19, 2025

Please note that due to inclement weather, the following scheduled roadwork activities may be postponed. We will provide updates on work as it is rescheduled.


In addition to the projects listed below that may impact your commute, you can find information on work being done to enhance our City on the Capital Improvement Projects Map and the Road Construction Map.


Irvine Center Drive Lane Closures

As part of the Irvine Center Drive Pavement Rehabilitation project, one lane is closed in each direction on Irvine Center Drive between Scientific and Tesla through Saturday, February 15.

The paving operation has been postponed due to the rain, with work scheduled to be completed and lanes reopened Saturday.

Irvine Center Drive Lane Closures

Northbound MacArthur Boulevard On-Ramp Extended Closure

Work is underway to reconstruct the northbound State Route 55 (SR-55) MacArthur Boulevard loop on-ramp. Due to inclement weather, the ramp is now expected to reopen to motorists on Wednesday, February 19.

The work is being done by OCTA in cooperation with Caltrans to improve 4 miles of SR-55 between the I-405 and I-5 Freeways. The project will add one regular lane and one carpool lane in each direction to help with traffic flow and improve mobility. Please visit octa.net/55Construction for more information.


Civic Center Parking Lot Rehabilitation

The Public Works & Sustainability Department continues to make improvements to the Civic Center Parking Lot, with Phase 1 beginning Tuesday, February 18. 

The project includes upgrades to the existing curbs, access ramps, and sidewalk adjacent to the building for ADA compliance, and removal of existing bollards to improve the entrance from the parking lot to the Civic Center.

Phase 1 will primarily impact the perimeter of the parking lot and is anticipated to last approximately four weeks (weather permitting). Work will be done Monday through Friday from 7 a.m. to 7 p.m. and may include weekend work as necessary.

The entire project is expected to be complete in July.

Civic Center Parking Lot Rehabilitation

Overnight Closure: Walnut Avenue, I-5 Freeway Ramps

As work continues on the next phase of the Jeffrey Open Space Trail Bicycle and Pedestrian Bridge, Walnut Avenue south of Jeffrey Road and the southbound I-5 Freeway on- and off-ramps at Jeffrey Road will be completely closed on the following dates:

  • Thursday, February 20, from 9 p.m. to Friday, February 21, at 7 a.m.
  • Friday, February 21, from 9 p.m. to Saturday, February 22, at 7 a.m.

Access to area residences and businesses will be maintained; however, there will be no access to the southbound I-5 Freeway on- and off-ramps or Caltrans Park & Ride during the overnight closure. 

The entire project is anticipated to be complete in March 2026.

Walnut