 FOR IMMEDIATE RELEASE
June 27, 2025
CONTACT
Aric Mitchell, PIO info@fortsmithpd.org 479-709-5000
STREET CLOSURE
MULTIPLE LOCATIONS FOR SEWER REPAIRS, STORM DRAIN IMPROVEMENTS, AND TRAFFIC SIGNAL POLE INSTALLATIONS
Fort Smith, AR - The following street closures have been approved for multiple cited reasons. Please see below for affected dates and times:
- S 28th St from Zero St to McKinnley Ave Present-July 27, 2025, All Day, Storm Drain Improvements
- Jacobs Ave between Ferguson and Hwy 271 Present-July 3, 2025, 6:30 AM-5 PM, Replacing Sewer Main
- 26th St between Osage and Phoenix Present-July 3, 2025, 6:30 AM-5 PM, Replacing Sewer Main
- Osage between S. 24th st and 26th and S. 25th St from Osage to Phoenix Present-July 9, 2025 6:30 AM-5 PM, Replacing Sewer Main
- Uma St from S 28th St to S 30th St Present-July 9, 2025, All Day, Sewer line and manholes
- Dallas Street and Massard Road Present-July 22, 2025, All Day, Replacing Traffic Signal Poles
- N 47th between J St and L St Present-July 15, 2025 All Day, Replacing Sewer Main
Keep up with street closures on our website as well at this link.
|
|
|
|