BRT Construction Look Ahead

Having trouble viewing this email? View it as a Web page.

Bus Rapid Transit

AC Transit is committed to a construction schedule that is timely, efficient and provides the most accurate information for those doing business or who call the 9.5-mile BRT corridor home. Members of our outreach team are on the BRT corridor daily to answer your questions and provide the latest updates.

Regular construction updates are also available on the BRT website in our Weekly Construction Updates section as well as on social media @rideactbrt.

Please note, field conditions and weather may impact schedules and construction zone locations. As we make progress on this $213 million investment in the community, AC Transit encourages businesses and residents alike to allow extra travel time.

April 16, 2018 through May 4, 2018

BRT Crews will be making infrastructure upgrades and building BRT in the following areas:

collageA

Zone 14:

San Leandro — E. 14th Street from Durant Avenue to Davis Street and on Davis Street from E.14th Street to San Leandro Boulevard.

  • Northwest corner of Davis Street and Dan Niemi Way
  • E. 14th at Georgia Way – BRT Georgia Way Station (Southbound) 
  • E. 14th at Georgia Way – BRT Georgia Way Station (Northbound)
  • E. 14th between Toler and Lorraine Boulevard– BRT Civic Center Station (Southbound)
  • Davis Street between E.14th and Hayes – BRT Downtown Station (Southbound)
  • E. 14th between Broadmoor and Bristol Boulevard – Durant Avenue Median Station
  • Southwest corner of W. Broadmoor and E. 14th Street

    Zone 13:

      Oakland — International Boulevard between 94th and Durant Avenues

      • Northwest corner of 100th Avenue and International Boulevard
      • Southwest corner of 100th Avenue and International Boulevard
      • 102nd Avenue and International Boulevard
      • 99th Avenue and International Boulevard
      • International Boulevard eastside sidewalk between 97th Avenue and 98th
      • 96th Avenue and International Boulevard

        Zone 12:

        Oakland —International Boulevard between 82nd and 94th

        • International Boulevard between 92nd Avenue and 94th Avenue
        • 90th Avenue and International Boulevard
        • International Boulevard between 88th Avenue and 89th Avenue
        •  International Boulevard between 82nd Avenue and 85th Avenue

        Zone 11:

        Oakland — International Boulevard between 71st and 82nd Avenues

        • Corners at 81st Avenue and International Boulevard
        • International Boulevard between 73rd Avenue and 78th Avenue

            Zone 8:

            Oakland — International Boulevard between 41st and 52nd Avenues

            • International Boulevard from 44th to 45th Avenues – BRT High Street Station
            • 50th Avenue and International Boulevard

            Zones 3 and 4:

            Oakland - International Boulevard and E. 12th Street between 14th and 2nd Avenues

            • E. 12th Street between 2nd Avenue and 14th Avenue

            Corridor Wide:

            ADA Ramp and Traffic Signal Foundation layout            


            collageB

            AC Transit encourages your feedback, and we’re ready to provide individualized BRT presentations to your neighborhood groups, community organizations and businesses. To make comments or ask questions or schedule a presentation, please contact our Outreach Team:

            BRT Information Center
            3322A International Boulevard
            Oakland CA 94601

            brt@actransit.org | 510.891.5478

            To learn more, visit the BRT website and follow us on Facebook, Twitter or Instagram.

            About AC Transit Bus Rapid Transit (BRT) Project:
            BRT is a bus service that mirrors the frequency, reliability and safety of light-rail train service without the high cost. BRT will operate along a 9.5-mile corridor between downtown Oakland and the San Leandro BART Station, primarily along International Boulevard and East 14th Street.