City of Lynnwood Project Update - 33rd Ave W Extension March 6, 2015

Home Email Subscription RSS Facebook
Lynnwood Washington

Project Update - 33rd Avenue West Extension

The project will complete a new roadway through the proposed Lynnwood Place development (Costco). A new intersection will be constructed on 184th Street SW just east of the existing 33rd Avenue W intersection.  The new roadway will extend north from the new intersection to the existing intersection at Alderwood Mall Parkway and Maple Road.  

33rd project picture 3-6-15

Last week, more concrete sidewalk, ADA Ramps and the North Entrance cross walk pours occurred. Also, the electrical subcontractor poured more illumination and ped bases primarily at the North end of the project. 

This week, the landscaper mobilized and commenced preparation of planter beds, followed by irrigation and some topsoil placement. The paving of asphalt sidewalks occurred on Monday along the western side of 33rd from 184th up to 30th Ave. The electrical subcontractor formed and poured more illumination, cabinet and ped bases.

Next week, the irrigation will continue, followed by more topsoil and subsequent planting. The deep drilling of special signal pole foundations is expected to start Wednesday with 184th, moving on Thursday/Friday to the work at the Alderwood Mall Parkway intersection. The underground boring work for its conduit in the intersection is planned to follow in the subsequent week.